Integrating posture‐hour constraints into construction scheduling to enhance workforce wellbeing

This study introduces a new posture-hour-based scheduling framework that integrates ergonomic constraints into construction planning. It shifts the traditional focus from “labor-hours” to “posture-hours” as a primary resource unit. The novelty lies in (1) defining and formulating this new problem in practical construction settings and (2) developing algorithms that treat posture capacity as an allocatable resource. This approach proactively manages musculoskeletal disorder risks by accounting for each activity's posture-specific demands and workers' posture-holding capacities as scheduling limits. Validated via a benchmark case and a real-world concrete pouring project, applying the framework significantly reduces cumulative exposure to high-risk postures, compared to traditional methods. While it may slightly increase project duration, this trade-off better balances physical workload, prevents posture-induced health issues, and enhances long-term workforce wellbeing and sustainability. This interdisciplinary research provides a foundational framework for integrating occupational health considerations, labor productivity metrics, and construction planning methodologies.

Authors

Institutions

Publication Details

Journal
Computer-Aided Civil and Infrastructure Engineering
Published
2025-11-25
DOI
https://doi.org/10.1111/mice.70140
Primary Topic
Occupational Health and Safety Research
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Integrating posture‐hour constraints into construction scheduling to enhance workforce wellbeing

Ming Lu, Kai Qi
Computer-Aided Civil and Infrastructure Engineering
Occupational Health and Safety Research
article

Integrating posture‐hour constraints into construction scheduling to enhance workforce wellbeing

Ming Lu, Kai Qi
article en

Abstract

This study introduces a new posture-hour-based scheduling framework that integrates ergonomic constraints into construction planning. It shifts the traditional focus from “labor-hours” to “posture-hours” as a primary resource unit. The novelty lies in (1) defining and formulating this new problem in practical construction settings and (2) developing algorithms that treat posture capacity as an allocatable resource. This approach proactively manages musculoskeletal disorder risks by accounting for each activity's posture-specific demands and workers' posture-holding capacities as scheduling limits. Validated via a benchmark case and a real-world concrete pouring project, applying the framework significantly reduces cumulative exposure to high-risk postures, compared to traditional methods. While it may slightly increase project duration, this trade-off better balances physical workload, prevents posture-induced health issues, and enhances long-term workforce wellbeing and sustainability. This interdisciplinary research provides a foundational framework for integrating occupational health considerations, labor productivity metrics, and construction planning methodologies.

Computer-Aided Civil and Infrastructure EngineeringVol. 40(30)
Hong Kong Polytechnic University (HK)
Openalex Percentile: Top 51%
Occupational Health and Safety Research
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.