Credible capacity evaluation of virtual power plants considering wind and PV uncertainties

The increasing integration of weather-dependent renewable energy sources into Virtual Power Plants (VPPs) introduces significant uncertainty in short-term dispatch planning. This paper develops a comprehensive decision-making framework that jointly optimizes credible capacity allocation and operational dispatch under forecast uncertainty. We first compare three probabilistic forecasting methods-Bayesian Neural Networks (BNN), Quantile Regression Forests (QRF), and Gradient Boosted Decision Trees (GBDT)-to quantify wind and solar variability, using metrics such as root mean square error (RMSE), continuous ranked probability score (CRPS), and empirical coverage. BNN is selected as the primary forecasting tool due to its superior calibration and robustness across both resource types. A distributionally robust optimization (DRO) model is then formulated using a Wasserstein ambiguity set and a Conditional Value-at-Risk (CVaR) objective to hedge against worst-case renewable output scenarios. Empirical data from a stylized VPP system comprising 340 kW of installed renewables and urban mixed loads is used to evaluate the framework. Results indicate that the proposed DRO model reduces expected shortfall by up to 78% compared to deterministic baselines, and outperforms quantile-based models in both cost consistency and energy-not-supplied metrics. Scenario-based dispatch simulations reveal that increasing the CVaR confidence level from 90 to 99% improves system reliability from 95.1 to 99.7%, albeit with a 5.7% decline in expected profit. The analysis also quantifies the relative contribution of wind, solar, and load forecast errors to overall dispatch uncertainty. This work highlights the value of integrated probabilistic modelling and risk-aware optimization in enabling reliable and economically efficient VPP operations.

Authors

Institutions

Publication Details

Journal
Scientific Reports
Published
2025-11-25
DOI
https://doi.org/10.1038/s41598-025-26037-6
Citations
1
Primary Topic
Integrated Energy Systems Optimization
Type
article
Field-Weighted Citation Impact
0.73

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Credible capacity evaluation of virtual power plants considering wind and PV uncertainties

Chaojie Li, Youquan Jiang, Silin Zhu, Wen Yan et al.
1 citations
Scientific Reports
Integrated Energy Systems Optimization
0.73
article

Credible capacity evaluation of virtual power plants considering wind and PV uncertainties

Chaojie Li, Youquan Jiang, Silin Zhu, Wen Yan, Zhe Liu, Shijin Tian, Ruyue Guo, Jiang Dai
article en
1 citations

Abstract

The increasing integration of weather-dependent renewable energy sources into Virtual Power Plants (VPPs) introduces significant uncertainty in short-term dispatch planning. This paper develops a comprehensive decision-making framework that jointly optimizes credible capacity allocation and operational dispatch under forecast uncertainty. We first compare three probabilistic forecasting methods-Bayesian Neural Networks (BNN), Quantile Regression Forests (QRF), and Gradient Boosted Decision Trees (GBDT)-to quantify wind and solar variability, using metrics such as root mean square error (RMSE), continuous ranked probability score (CRPS), and empirical coverage. BNN is selected as the primary forecasting tool due to its superior calibration and robustness across both resource types. A distributionally robust optimization (DRO) model is then formulated using a Wasserstein ambiguity set and a Conditional Value-at-Risk (CVaR) objective to hedge against worst-case renewable output scenarios. Empirical data from a stylized VPP system comprising 340 kW of installed renewables and urban mixed loads is used to evaluate the framework. Results indicate that the proposed DRO model reduces expected shortfall by up to 78% compared to deterministic baselines, and outperforms quantile-based models in both cost consistency and energy-not-supplied metrics. Scenario-based dispatch simulations reveal that increasing the CVaR confidence level from 90 to 99% improves system reliability from 95.1 to 99.7%, albeit with a 5.7% decline in expected profit. The analysis also quantifies the relative contribution of wind, solar, and load forecast errors to overall dispatch uncertainty. This work highlights the value of integrated probabilistic modelling and risk-aware optimization in enabling reliable and economically efficient VPP operations.

Scientific ReportsVol. 15(1)
Qinghai University (CN), Guizhou Electric Power Design and Research Institute (CN)
China Southern Power Grid
Openalex Percentile: Top 21%
Integrated Energy Systems Optimization
0.73
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.