An estimated Time of Arrival (ETA) model for achieving Just-in-Time (JIT) modular construction delivery in high-density cities

Abstract Modular construction (MC) is a sound strategy to alleviate global issues such as housing crisis, labor shortage, and stagnant productivity. Project managers are aspired to achieve a Just-in-Time (JIT) delivery of their MC logistics. However, the efforts often fall short without the presence of a dedicated Estimated Time of Arrival (ETA) model. This study aims to bridge this gap by developing a MC-oriented ETA model. It does so by first identifying critical factors influencing ETA accuracy in general logistics and then developing an ETA model prototype, which is then calibrated using simulations and data collected from the Internet of Things (IoTs) applied in real-life MC projects in Hong Kong, China. Validated through a cross-border MC project in China’s Greater Bay Area, the MC-oriented ETA model achieved 90.6% prediction accuracy (±10 min), reduced transportation delays by 37.5%, and slashed daily planning time from 46.75 to 18.75 min. It is expected that the ETA model can be used in predictive planning of MC logistics delivery in the future. Ultimately, it can lead to the development of smart logistics planning and control systems to expedite MC housing delivery and alleviate urban congestion in high-density cities, offering valuable insights for policymakers, construction stakeholders, and supply chain managers.

Authors

Institutions

Publication Details

Journal
Frontiers of Engineering Management
Published
2025-11-22
DOI
https://doi.org/10.1007/s42524-025-5112-0
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

An estimated Time of Arrival (ETA) model for achieving Just-in-Time (JIT) modular construction delivery in high-density cities

Liupengfei Wu, Zhiming Dong, Lingling Wang, Bolun Wang et al.
Frontiers of Engineering Management
BIM and Construction Integration
article

An estimated Time of Arrival (ETA) model for achieving Just-in-Time (JIT) modular construction delivery in high-density cities

Liupengfei Wu, Zhiming Dong, Lingling Wang, Bolun Wang, Weisheng Lu
article en

Abstract

Abstract Modular construction (MC) is a sound strategy to alleviate global issues such as housing crisis, labor shortage, and stagnant productivity. Project managers are aspired to achieve a Just-in-Time (JIT) delivery of their MC logistics. However, the efforts often fall short without the presence of a dedicated Estimated Time of Arrival (ETA) model. This study aims to bridge this gap by developing a MC-oriented ETA model. It does so by first identifying critical factors influencing ETA accuracy in general logistics and then developing an ETA model prototype, which is then calibrated using simulations and data collected from the Internet of Things (IoTs) applied in real-life MC projects in Hong Kong, China. Validated through a cross-border MC project in China’s Greater Bay Area, the MC-oriented ETA model achieved 90.6% prediction accuracy (±10 min), reduced transportation delays by 37.5%, and slashed daily planning time from 46.75 to 18.75 min. It is expected that the ETA model can be used in predictive planning of MC logistics delivery in the future. Ultimately, it can lead to the development of smart logistics planning and control systems to expedite MC housing delivery and alleviate urban congestion in high-density cities, offering valuable insights for policymakers, construction stakeholders, and supply chain managers.

Frontiers of Engineering ManagementVol. 12(4)
Hong Kong Polytechnic University (HK), Lingnan University (HK), University of Hong Kong (HK)
Innovation and Technology Commission, Innovation and Technology Fund
Openalex Percentile: Top 62%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

An estimated Time of Arrival (ETA) model for achieving Just-in-Time (JIT) modular construction delivery in high-density cities — Liupengfei Wu, Zhiming Dong, et al. · Frontiers of Engineering Management (2025) | TGRS Research Map | TGRS