FAIR commissioning - Towards first science

The international Facility for Antiproton and Ion Research (FAIR) is under construction at the GSI Helmholtz Centre in Darmstadt. The first project stage includes the superconducting 100 Tm heavy-ion synchrotron SIS100, the Super Fragment Separator, and associated beam transport lines. Part of GSI’s existing accelerator chain, comprising UNILAC and SIS18, will serve as injector. Installation work in the FAIR accelerator tunnels and supply buildings has been ongoing since early 2024. As progress continues, special attention is now on the start of commissioning, beginning in 2025 with the cryogenic plant. Commissioning of the transport line will follow at the end of 2025, and beam commissioning is scheduled for the second half of 2027. This paper outlines the current status of the project, commissioning strategy and timeline.

Authors

Publication Details

Journal
ArXiv.org
Published
2025-11-05
DOI
https://doi.org/10.18429/jacow-ipac2025-thbn2
Citations
1
Primary Topic
Superconducting Materials and Applications
Type
article
Field-Weighted Citation Impact
0.67
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

FAIR commissioning - Towards first science

P. Gasik, S. Piétri, H. Kollmus, R. Aßmann et al.
1 citations
ArXiv.org
Superconducting Materials and Applications
0.67
article

FAIR commissioning - Towards first science

P. Gasik, S. Piétri, H. Kollmus, R. Aßmann, H. Simon, Stephan Schwarz, Oksana Geithner, Peter Spiller, M. Kauschke, F. Hagenbuck, Stephan Reimann, N. Pyka, K. Vogt, V. Kamerdzhiev, T. Radon, C. Schroeder, P. Hofmann, A. Herlert, H. Albers
article en
1 citations

Abstract

The international Facility for Antiproton and Ion Research (FAIR) is under construction at the GSI Helmholtz Centre in Darmstadt. The first project stage includes the superconducting 100 Tm heavy-ion synchrotron SIS100, the Super Fragment Separator, and associated beam transport lines. Part of GSI’s existing accelerator chain, comprising UNILAC and SIS18, will serve as injector. Installation work in the FAIR accelerator tunnels and supply buildings has been ongoing since early 2024. As progress continues, special attention is now on the start of commissioning, beginning in 2025 with the cryogenic plant. Commissioning of the transport line will follow at the end of 2025, and beam commissioning is scheduled for the second half of 2027. This paper outlines the current status of the project, commissioning strategy and timeline.

ArXiv.org
Openalex Percentile: Top 25%
Superconducting Materials and Applications
0.67
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

FAIR commissioning - Towards first science — P. Gasik, S. Piétri, et al. · ArXiv.org (2025) | TGRS Research Map | TGRS