A Study on Improvement Plans for Acceleration Work of Mechanical Equipment Work

This study explores the causes and challenges of acceleration work in mechanical equipment projects and proposes strategies for improvement. Acceleration work, often triggered by schedule delays, design changes, or client directives, necessitates intensive resource inputs within a limited timeframe. This pressure can lead to quality issues, safety risks, and cost overruns. Through an analysis of relevant legal precedents, a review of existing scholarly works, and insights from expert consultations, the research identifies phase-specific practical measures and highlights the importance of systematic documentation in supporting cost claims. Key policy recommendations include revising government contract guidelines to incorporate provisions for direct labor costs and enhancing subcontract agreements to clarify indirect costs. The goal of this research is to foster safer, higher-quality, and more dispute-resistant mechanical equipment projects.

Authors

Publication Details

Journal
Korean Journal of Air-Conditioning and Refrigeration Engineering
Published
2025-11-06
DOI
https://doi.org/10.6110/kjacr.2025.37.11.545
Primary Topic
Construction Engineering and Safety
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A Study on Improvement Plans for Acceleration Work of Mechanical Equipment Work

Y.S. Lee, H. M. Yun
Korean Journal of Air-Conditioning and Refrigeration Engineering
Construction Engineering and Safety
article

A Study on Improvement Plans for Acceleration Work of Mechanical Equipment Work

Y.S. Lee, H. M. Yun
article en

Abstract

This study explores the causes and challenges of acceleration work in mechanical equipment projects and proposes strategies for improvement. Acceleration work, often triggered by schedule delays, design changes, or client directives, necessitates intensive resource inputs within a limited timeframe. This pressure can lead to quality issues, safety risks, and cost overruns. Through an analysis of relevant legal precedents, a review of existing scholarly works, and insights from expert consultations, the research identifies phase-specific practical measures and highlights the importance of systematic documentation in supporting cost claims. Key policy recommendations include revising government contract guidelines to incorporate provisions for direct labor costs and enhancing subcontract agreements to clarify indirect costs. The goal of this research is to foster safer, higher-quality, and more dispute-resistant mechanical equipment projects.

Korean Journal of Air-Conditioning and Refrigeration EngineeringVol. 37(11)
Openalex Percentile: Top 66%
Construction Engineering and Safety
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.