Research on Construction Period Estimation Method for Hydropower Projects During Rainy Season Based on Monte Carlo Model

Aiming at the problem that traditional methods tend to have serious risks of underestimation or overestimation in the construction period prediction of hydropower projects during the rainy season, this paper intends to realize the scientific prediction of the construction period through the Monte Carlo model. Traditional methods rely on single-point estimation, making it difficult to handle random factors such as rainfall intensity and equipment failure, as well as the impact of risk superposition, which leads to deviations in construction period judgment. The research first sorts out key risk factors such as natural environment and construction resources, and assigns probability distributions to them based on historical data and expert judgment; then constructs a construction period calculation model that includes process dependencies and connection logic; conducts tens of thousands of random simulations using Python to generate a probability histogram and cumulative distribution curve of the construction period, which intuitively present the occurrence frequency and compliance probability of different construction periods. The results show that this method can effectively quantify uncertainties, accurately capture the impact of risk superposition, and provide construction period references for projects under multiple probability scenarios. Its application promotes the transformation of construction period management for hydropower projects during the rainy season from experience-based judgment to data-driven decision-making, improving the project's risk resistance and management scientificity.

Authors

Publication Details

Journal
Theory and Practice of Science and Technology
Published
2025-01-01
DOI
https://doi.org/10.47297/taposatwsp2633-456918.20250608
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Research on Construction Period Estimation Method for Hydropower Projects During Rainy Season Based on Monte Carlo Model

Pan Jiale
Theory and Practice of Science and Technology
Construction Project Management and Performance
article

Research on Construction Period Estimation Method for Hydropower Projects During Rainy Season Based on Monte Carlo Model

Pan Jiale
article en

Abstract

Aiming at the problem that traditional methods tend to have serious risks of underestimation or overestimation in the construction period prediction of hydropower projects during the rainy season, this paper intends to realize the scientific prediction of the construction period through the Monte Carlo model. Traditional methods rely on single-point estimation, making it difficult to handle random factors such as rainfall intensity and equipment failure, as well as the impact of risk superposition, which leads to deviations in construction period judgment. The research first sorts out key risk factors such as natural environment and construction resources, and assigns probability distributions to them based on historical data and expert judgment; then constructs a construction period calculation model that includes process dependencies and connection logic; conducts tens of thousands of random simulations using Python to generate a probability histogram and cumulative distribution curve of the construction period, which intuitively present the occurrence frequency and compliance probability of different construction periods. The results show that this method can effectively quantify uncertainties, accurately capture the impact of risk superposition, and provide construction period references for projects under multiple probability scenarios. Its application promotes the transformation of construction period management for hydropower projects during the rainy season from experience-based judgment to data-driven decision-making, improving the project's risk resistance and management scientificity.

Theory and Practice of Science and TechnologyVol. 6(8)
Openalex Percentile: Top 62%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.