Research on the Contagion Paths and Blocking Strategies of Schedule Risk in Prefabricated Buildings Under the EPC Mode

Against the backdrop of policy-driven transformation in construction industrialization, the EPC general contracting model has emerged as a core pathway for the large-scale development of prefabricated buildings. However, the EPC mode integrates the links of design, procurement, production, and transportation, construction, resulting in a complex coupling correlation among the risk factors of prefabricated construction schedule, which is easy to induce the risk contagion effect and increase the difficulty of risk control of project schedule delay. To address this, this study constructs a hybrid model integrating the “Fuzzy Interpretive Structural Model (FISM)-Coupling Degree Model-Bayesian Network (BN)” to systematically analyze risk contagion mechanisms. Taking an EPC prefabricated building project as an example, FISM is used to reveal the hierarchical structure of risk factors, while the coupling degree model quantifies interaction strengths and maps them into the BN to optimize conditional probability parameters. Through comprehensive hazard analysis, seven key causal risk factors and two critical risk propagation paths are identified. Targeted control measures are designed for the key risk factors, and BN-based simulation is applied to locate critical risk nodes and implement break-chain interventions for the risk paths, resulting in a 23% reduction in the probability of schedule delay. Engineering applications demonstrate that this model can effectively achieve the dynamic identification and blocking of risk paths, providing valuable reference for similar projects and offering informed support for managers in formulating scientific response strategies.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2025-11-02
DOI
https://doi.org/10.3390/buildings15213948
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Research on the Contagion Paths and Blocking Strategies of Schedule Risk in Prefabricated Buildings Under the EPC Mode

Yong Tian, Yanjuan Tang
Buildings
Construction Project Management and Performance
article

Research on the Contagion Paths and Blocking Strategies of Schedule Risk in Prefabricated Buildings Under the EPC Mode

Yong Tian, Yanjuan Tang
article en

Abstract

Against the backdrop of policy-driven transformation in construction industrialization, the EPC general contracting model has emerged as a core pathway for the large-scale development of prefabricated buildings. However, the EPC mode integrates the links of design, procurement, production, and transportation, construction, resulting in a complex coupling correlation among the risk factors of prefabricated construction schedule, which is easy to induce the risk contagion effect and increase the difficulty of risk control of project schedule delay. To address this, this study constructs a hybrid model integrating the “Fuzzy Interpretive Structural Model (FISM)-Coupling Degree Model-Bayesian Network (BN)” to systematically analyze risk contagion mechanisms. Taking an EPC prefabricated building project as an example, FISM is used to reveal the hierarchical structure of risk factors, while the coupling degree model quantifies interaction strengths and maps them into the BN to optimize conditional probability parameters. Through comprehensive hazard analysis, seven key causal risk factors and two critical risk propagation paths are identified. Targeted control measures are designed for the key risk factors, and BN-based simulation is applied to locate critical risk nodes and implement break-chain interventions for the risk paths, resulting in a 23% reduction in the probability of schedule delay. Engineering applications demonstrate that this model can effectively achieve the dynamic identification and blocking of risk paths, providing valuable reference for similar projects and offering informed support for managers in formulating scientific response strategies.

BuildingsVol. 15(21)
Shihezi University (CN)
Openalex Percentile: Top 62%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Research on the Contagion Paths and Blocking Strategies of Schedule Risk in Prefabricated Buildings Under the EPC Mode — Yong Tian, Yanjuan Tang · Buildings (2025) | TGRS Research Map | TGRS