Multi-stage structural identification of a tall timber building during construction: The role of connections and non-structural elements

Understanding the dynamic behaviour of timber buildings is essential for accurate vibration serviceability modelling, yet remains underexplored due to complexities in connection behaviour and contributions of non-structural elements. The study investigates these aspects through the case of Fyrtornet, a newly constructed 51 m tall 11-storey timber building in Sweden, featuring a glued-laminated timber (GLT) truss system and cross-laminated timber (CLT) slabs, as well as a CLT core. Ambient vibration testing was conducted at seven construction stages. For each stage, a finite element model was developed and updated based on the measured modal properties. The research identifies the progression of stiffness contributions of GLT and CLT connections, the foundation, and the glass façade. Results show that while the GLT connection stiffness changes during construction, it reaches a value consistent with a rigid behaviour. This observation was attributed to the installation of screed and partition walls before the final construction stage. In the earlier stages, the slip modulus equation provided by EC 1995-1-1 appears to offer a suitable estimate for GLT connection stiffness. Another important observation was that the foundation exhibited characteristics of a rigid boundary condition. Finally, the stiffness contribution of the glass façade was minimal. • Ambient vibration tests were performed seven times during the construction of a 51 m tall timber building. • The slip modulus of the timber connections increased during construction. • The glass façade had minimal structural impact, likely due to its flexible mounting system. • Foundation stiffness evolved from flexible to rigid-like as construction progressed.

Authors

Institutions

Publication Details

Journal
Journal of Building Engineering
Published
2025-10-31
DOI
https://doi.org/10.1016/j.jobe.2025.114458
Citations
1
Primary Topic
Wood Treatment and Properties
Type
article
Field-Weighted Citation Impact
1.01
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Multi-stage structural identification of a tall timber building during construction: The role of connections and non-structural elements

Carl Larsson, Blaž Kurent, Osama Abdeljaber, Michael Dorn
1 citations
Journal of Building Engineering
Wood Treatment and Properties
1.01
article

Multi-stage structural identification of a tall timber building during construction: The role of connections and non-structural elements

Carl Larsson, Blaž Kurent, Osama Abdeljaber, Michael Dorn
article en
1 citations

Abstract

Understanding the dynamic behaviour of timber buildings is essential for accurate vibration serviceability modelling, yet remains underexplored due to complexities in connection behaviour and contributions of non-structural elements. The study investigates these aspects through the case of Fyrtornet, a newly constructed 51 m tall 11-storey timber building in Sweden, featuring a glued-laminated timber (GLT) truss system and cross-laminated timber (CLT) slabs, as well as a CLT core. Ambient vibration testing was conducted at seven construction stages. For each stage, a finite element model was developed and updated based on the measured modal properties. The research identifies the progression of stiffness contributions of GLT and CLT connections, the foundation, and the glass façade. Results show that while the GLT connection stiffness changes during construction, it reaches a value consistent with a rigid behaviour. This observation was attributed to the installation of screed and partition walls before the final construction stage. In the earlier stages, the slip modulus equation provided by EC 1995-1-1 appears to offer a suitable estimate for GLT connection stiffness. Another important observation was that the foundation exhibited characteristics of a rigid boundary condition. Finally, the stiffness contribution of the glass façade was minimal. • Ambient vibration tests were performed seven times during the construction of a 51 m tall timber building. • The slip modulus of the timber connections increased during construction. • The glass façade had minimal structural impact, likely due to its flexible mounting system. • Foundation stiffness evolved from flexible to rigid-like as construction progressed.

Journal of Building EngineeringVol. 115
University of Ljubljana (SI), Linnaeus University (SE)
Openalex Percentile: Top 19%
Wood Treatment and Properties
1.01
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.