Comparative Risk Prioritization in the Initiation Phase of the Pagerungan Besar Photovoltaic Plant: A Failure Mode and Effect Analysis (FMEA) and Risk Matrix Approach

Photovoltaic (PV) power plant projects in East Java often face challenges during the initiation phase due to inadequate risk assessments. This phase is crucial for ensuring the project's long-term success; however, suboptimal risk identification has caused project delays. In the risk assessment process, high-priority risks need to be mitigated, but differences in the methods used can result in varying risk priority outcomes. One of the methods that can be used is Failure Mode and Effect Analysis (FMEA), while according to internal regulations at PT PLN (Persero), the Risk Matrix is applied. By using these two methods, the differences in the resulting risk priority rankings can be identified. Both tools rely on evaluations from experts experienced in decision-making during the initiation phase of PV power plant projects. From the analysis, 12 risks were identified during the initiation phase of the Pagerungan Besar PV power plant project. The highest-priority risks identified include Suboptimal feasibility study (Risk Priority Number/RPN: 74.27), unfavorable outcomes for the organization/company (RPN: 68.96), lack of budget (RPN: 64.00), and stakeholder Intervention (RPN: 53.69). Meanwhile, by plotting the Severity Level and Occurrence Level of each risk on the Risk Matrix according to PT PLN (Persero) regulations, the highest-priority risks identified include Suboptimal feasibility study (Extreme Risk Level, Zone E5), location-related issues (Extreme Risk Level, Zone E5), non-compliance with regulations (Extreme Risk Level, Zone E5), and suboptimal project team (Very High Risk Level, Zone D5). The two risk assessment methods produced different prioritizations, potentially impacting mitigation strategy decisions. This variation highlights the need for further analysis to ensure accurate and reliable risk prioritization, which is critical for project success and efficient resource allocation. Future studies should focus on evaluating prioritization methods to support effective decision-making and ensure timely project implementation in line with the targeted Commercial Operation Date (COD).

Authors

Institutions

Publication Details

Journal
IPTEK Journal of Engineering
Published
2025-08-31
DOI
https://doi.org/10.12962/j23378557.v11i2.a22667
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Comparative Risk Prioritization in the Initiation Phase of the Pagerungan Besar Photovoltaic Plant: A Failure Mode and Effect Analysis (FMEA) and Risk Matrix Approach

Ervina Ahyudanari, Agustina Dwi Retnaningtias
IPTEK Journal of Engineering
Occupational Health and Safety Management
article

Comparative Risk Prioritization in the Initiation Phase of the Pagerungan Besar Photovoltaic Plant: A Failure Mode and Effect Analysis (FMEA) and Risk Matrix Approach

Ervina Ahyudanari, Agustina Dwi Retnaningtias
article en

Abstract

Photovoltaic (PV) power plant projects in East Java often face challenges during the initiation phase due to inadequate risk assessments. This phase is crucial for ensuring the project's long-term success; however, suboptimal risk identification has caused project delays. In the risk assessment process, high-priority risks need to be mitigated, but differences in the methods used can result in varying risk priority outcomes. One of the methods that can be used is Failure Mode and Effect Analysis (FMEA), while according to internal regulations at PT PLN (Persero), the Risk Matrix is applied. By using these two methods, the differences in the resulting risk priority rankings can be identified. Both tools rely on evaluations from experts experienced in decision-making during the initiation phase of PV power plant projects. From the analysis, 12 risks were identified during the initiation phase of the Pagerungan Besar PV power plant project. The highest-priority risks identified include Suboptimal feasibility study (Risk Priority Number/RPN: 74.27), unfavorable outcomes for the organization/company (RPN: 68.96), lack of budget (RPN: 64.00), and stakeholder Intervention (RPN: 53.69). Meanwhile, by plotting the Severity Level and Occurrence Level of each risk on the Risk Matrix according to PT PLN (Persero) regulations, the highest-priority risks identified include Suboptimal feasibility study (Extreme Risk Level, Zone E5), location-related issues (Extreme Risk Level, Zone E5), non-compliance with regulations (Extreme Risk Level, Zone E5), and suboptimal project team (Very High Risk Level, Zone D5). The two risk assessment methods produced different prioritizations, potentially impacting mitigation strategy decisions. This variation highlights the need for further analysis to ensure accurate and reliable risk prioritization, which is critical for project success and efficient resource allocation. Future studies should focus on evaluating prioritization methods to support effective decision-making and ensure timely project implementation in line with the targeted Commercial Operation Date (COD).

IPTEK Journal of EngineeringVol. 11(2)
Sepuluh Nopember Institute of Technology (ID)
Openalex Percentile: Top 54%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.