The impact of the number of preemptions in resource-constrained project scheduling problems with time-varying resources: computational experiments and a case study

Abstract This paper addresses the preemptive version of the resource-constrained project scheduling problem (RCPSP), with the aim of assessing the impact of the number of preemptions on project makespan. In fact, preempting some activity can reduce the makespan, but it may have the undesired effect of requiring a surplus of coordination in the project team. Hence, we consider the bicriteria problem of minimizing makespan and number of preemptions, and using a suitable integer linear programming formulation we compute the Pareto front for a sample of 30-job benchmark instances. Resource availability can either remain constant or can vary over time (according to a known schedule), as typical of situations in which the same resources are shared among various projects. We perform a detailed analysis of the impact of preemptions on project makespan, and how it is related to structural parameters of RCPSP instances. Among other results, we find that most often very few preemptions are enough to achieve most of the benefit. Also, the utility in introducing preemptions is significantly higher when resources vary over time. The proposed solution approach is then applied to a case study in Information Technology (IT) project management, showing how preemptions and efficiency can be traded off in practice.

Authors

Institutions

Publication Details

Journal
Annals of Operations Research
Published
2025-10-29
DOI
https://doi.org/10.1007/s10479-025-06892-2
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

The impact of the number of preemptions in resource-constrained project scheduling problems with time-varying resources: computational experiments and a case study

Alessandro Agnetis, Ilaria Salvadori
Annals of Operations Research
Resource-Constrained Project Scheduling
article

The impact of the number of preemptions in resource-constrained project scheduling problems with time-varying resources: computational experiments and a case study

Alessandro Agnetis, Ilaria Salvadori
article en

Abstract

Abstract This paper addresses the preemptive version of the resource-constrained project scheduling problem (RCPSP), with the aim of assessing the impact of the number of preemptions on project makespan. In fact, preempting some activity can reduce the makespan, but it may have the undesired effect of requiring a surplus of coordination in the project team. Hence, we consider the bicriteria problem of minimizing makespan and number of preemptions, and using a suitable integer linear programming formulation we compute the Pareto front for a sample of 30-job benchmark instances. Resource availability can either remain constant or can vary over time (according to a known schedule), as typical of situations in which the same resources are shared among various projects. We perform a detailed analysis of the impact of preemptions on project makespan, and how it is related to structural parameters of RCPSP instances. Among other results, we find that most often very few preemptions are enough to achieve most of the benefit. Also, the utility in introducing preemptions is significantly higher when resources vary over time. The proposed solution approach is then applied to a case study in Information Technology (IT) project management, showing how preemptions and efficiency can be traded off in practice.

Annals of Operations Research
University of Siena (IT)
Università degli Studi di Siena
Openalex Percentile: Top 63%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

The impact of the number of preemptions in resource-constrained project scheduling problems with time-varying resources: computational experiments and a case study — Alessandro Agnetis, Ilaria Salvadori · Annals of Operations Research (2025) | TGRS Research Map | TGRS