Integrating Machine Learning and Engineering Management to Optimize Construction Scheduling and Resource Allocation

The construction industry is increasingly confronted by the uncertainty of megaprojects, site variation, and the need to deliver low cost and on time.Traditional approaches to scheduling and resource management such as the Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) cannot account for uncertainty, maintain pace with in-progress changes, or benefit from growth in digital data availability.This article proposes an integrated framework that brings together machine learning (ML) techniques and engineering management practices to realign construction scheduling and resource allocation to optimize.Supervised models and deep learning models are utilized to forecast task durations and delay risks from historical project data, sensor reading data, and Building Information Modelling (BIM)-indexed datasets.Clustering methods are utilized to cluster tasks and resources in order to minimize the complexity of scheduling, and reinforcement learning (RL) agents adaptively modify allocations with uncertainty.For providing feasibility and satisfaction of engineering constraints, RL outputs are verified by mixed-integer linear programming (MILP).The approach is tested with simulated data and case studies and achieves significant improvement in project completion time, resource allocation, and tolerance to delay compared to conventional methods.The findings countenances that ML-based decision-making has immense potential in transforming construction management practice.

Publication Details

Journal
International Journal of Science and Engineering Applications
Published
2025-10-29
DOI
https://doi.org/10.7753/ijsea1411.1008
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Integrating Machine Learning and Engineering Management to Optimize Construction Scheduling and Resource Allocation

International Journal of Science and Engineering Applications
Resource-Constrained Project Scheduling
article

Integrating Machine Learning and Engineering Management to Optimize Construction Scheduling and Resource Allocation

article en

Abstract

The construction industry is increasingly confronted by the uncertainty of megaprojects, site variation, and the need to deliver low cost and on time.Traditional approaches to scheduling and resource management such as the Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) cannot account for uncertainty, maintain pace with in-progress changes, or benefit from growth in digital data availability.This article proposes an integrated framework that brings together machine learning (ML) techniques and engineering management practices to realign construction scheduling and resource allocation to optimize.Supervised models and deep learning models are utilized to forecast task durations and delay risks from historical project data, sensor reading data, and Building Information Modelling (BIM)-indexed datasets.Clustering methods are utilized to cluster tasks and resources in order to minimize the complexity of scheduling, and reinforcement learning (RL) agents adaptively modify allocations with uncertainty.For providing feasibility and satisfaction of engineering constraints, RL outputs are verified by mixed-integer linear programming (MILP).The approach is tested with simulated data and case studies and achieves significant improvement in project completion time, resource allocation, and tolerance to delay compared to conventional methods.The findings countenances that ML-based decision-making has immense potential in transforming construction management practice.

International Journal of Science and Engineering Applications
Openalex Percentile: Top 63%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Integrating Machine Learning and Engineering Management to Optimize Construction Scheduling and Resource Allocation · International Journal of Science and Engineering Applications (2025) | TGRS Research Map | TGRS