DELAYS IN RAILWAY CONSTRUCTION: INSIGHTS FROM THE CONTRACTOR’S PERSPECTIVE

The construction sector in Malaysia has undergone rapid expansion, significantly contributing to the nation's GDP and supporting various other industries. However, this rapid development—particularly in infrastructure projects within Selangor—has faced notable challenges. One such challenge is the persistent delay in railway construction projects, including the Mass Rapid Transit (MRT) system. This study investigates the primary causes of these delays from the contractor's perspective, evaluates their impacts, and proposes mitigation strategies. Employing Structural Equation Modelling (SEM) for analysis, the research identifies key delay factors such as material procurement difficulties, regulatory constraints, and environmental issues. The findings offer valuable insights into enhancing project timelines and improving overall productivity in railway infrastructure development, ultimately contributing to more effective project management practices.

Authors

Institutions

Publication Details

Journal
International Journal of Innovation and Industrial Revolution
Published
2025-09-30
DOI
https://doi.org/10.35631/ijirev.722050
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

DELAYS IN RAILWAY CONSTRUCTION: INSIGHTS FROM THE CONTRACTOR’S PERSPECTIVE

Mohd Rafe Abdul Majid, Juzailah Nur Yunus, Raja Nor Husna Raja Mohd Noor, Hariez Izhan Abdul Rani
International Journal of Innovation and Industrial Revolution
Construction Project Management and Performance
article

DELAYS IN RAILWAY CONSTRUCTION: INSIGHTS FROM THE CONTRACTOR’S PERSPECTIVE

Mohd Rafe Abdul Majid, Juzailah Nur Yunus, Raja Nor Husna Raja Mohd Noor, Hariez Izhan Abdul Rani
article en

Abstract

The construction sector in Malaysia has undergone rapid expansion, significantly contributing to the nation's GDP and supporting various other industries. However, this rapid development—particularly in infrastructure projects within Selangor—has faced notable challenges. One such challenge is the persistent delay in railway construction projects, including the Mass Rapid Transit (MRT) system. This study investigates the primary causes of these delays from the contractor's perspective, evaluates their impacts, and proposes mitigation strategies. Employing Structural Equation Modelling (SEM) for analysis, the research identifies key delay factors such as material procurement difficulties, regulatory constraints, and environmental issues. The findings offer valuable insights into enhancing project timelines and improving overall productivity in railway infrastructure development, ultimately contributing to more effective project management practices.

International Journal of Innovation and Industrial RevolutionVol. 7(22)
Universiti Teknologi MARA (MY)
Universiti Teknologi MARA
Openalex Percentile: Top 63%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.