Estimating the effects of ramp-up and learning from cost performance data

Purpose The US Department of Defense routinely receives monthly cost performance reports (CPRs) to monitor program status, justify payments and identify production issues. This paper investigates how ramp-up, disruption and learning affect costs in long-cycle, made-to-order defense production. Using CPR data from the US Army’s Black Hawk helicopter program, we estimate cost due to learning and production rate. We show how disruptions and experimentation altered production. Design/methodology/approach We estimate parameters of the Camm and Womer (1987) model of crew allocation from 133 months of CPR data spanning five Black Hawk lots (1977–1982). To separate learning-driven cost reductions from ramp-up and disruption effects, parameters are estimated from a later, stable period of production, then applied to earlier disrupted periods. Simulations compare predicted costs under optimal ramp-up with observed outcomes. Findings Results show a steep underlying learning curve of about 71% when production rate effects are considered. In contrast, observed curves appear flatter when ramp-up is ignored. Simulations suggest that better planning with smoother ramp-up could have reduced labor requirements by 13,000–15,500 worker months and program start could have been delayed by nearly two years. Practical implications Our approach provides defense managers with a new way to use CPR data to validate contractor cost-at-completion estimates early in programs. The model helps estimate the impact of disruptions, project labor requirements and evaluate schedule alternatives. While based on a historical case, the framework can be applied to current acquisition programs, offering insights into cost, schedule and risk trade-offs during ramp-up. Originality/value This research is the first to use CPR data for these purposes.

Authors

Institutions

Publication Details

Journal
Journal of Defense Analytics and Logistics
Published
2025-10-28
DOI
https://doi.org/10.1108/jdal-02-2025-0003
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Estimating the effects of ramp-up and learning from cost performance data

Jeffrey D. Camm, Norman Keith Womer, Bashir Al-Abedalla, Haitao Li
Journal of Defense Analytics and Logistics
Construction Project Management and Performance
article

Estimating the effects of ramp-up and learning from cost performance data

Jeffrey D. Camm, Norman Keith Womer, Bashir Al-Abedalla, Haitao Li
article en

Abstract

Purpose The US Department of Defense routinely receives monthly cost performance reports (CPRs) to monitor program status, justify payments and identify production issues. This paper investigates how ramp-up, disruption and learning affect costs in long-cycle, made-to-order defense production. Using CPR data from the US Army’s Black Hawk helicopter program, we estimate cost due to learning and production rate. We show how disruptions and experimentation altered production. Design/methodology/approach We estimate parameters of the Camm and Womer (1987) model of crew allocation from 133 months of CPR data spanning five Black Hawk lots (1977–1982). To separate learning-driven cost reductions from ramp-up and disruption effects, parameters are estimated from a later, stable period of production, then applied to earlier disrupted periods. Simulations compare predicted costs under optimal ramp-up with observed outcomes. Findings Results show a steep underlying learning curve of about 71% when production rate effects are considered. In contrast, observed curves appear flatter when ramp-up is ignored. Simulations suggest that better planning with smoother ramp-up could have reduced labor requirements by 13,000–15,500 worker months and program start could have been delayed by nearly two years. Practical implications Our approach provides defense managers with a new way to use CPR data to validate contractor cost-at-completion estimates early in programs. The model helps estimate the impact of disruptions, project labor requirements and evaluate schedule alternatives. While based on a historical case, the framework can be applied to current acquisition programs, offering insights into cost, schedule and risk trade-offs during ramp-up. Originality/value This research is the first to use CPR data for these purposes.

Journal of Defense Analytics and LogisticsVol. 9(2)
University of Jordan (JO), University of Missouri–St. Louis (US), Virginia Tech - Wake Forest University School of Biomedical Engineering & Sciences (US), Wake Forest University (US)
U.S. Department of Transportation, University of Nebraska-Lincoln, Mid-America Transportation Center, University of Nebraska-Lincoln
Openalex Percentile: Top 64%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.