Risk Prediction in Road Infrastructure Projects Considering Project Complexity Coefficients

Risks causing delays in the construction of roads and highways frequently lead to substantial economic and social consequences, with project timelines extending up to three times beyond their initial schedules. These risks not only extend the project timeline but also escalate the overall project execution cost. Despite extensive research on construction-related risks globally, a notable gap remains in studies specifically addressing the risk factors that cause delays in road projects. Analysing completed projects is crucial to derive practical and applicable results, as they offer essential insights into the real-world challenges and risks that may cause timeline extensions and budget escalations. Such an approach ensures that the findings are grounded in actual project outcomes, thereby enhancing their relevance and effectiveness in improving future project planning and risk management. For these reasons, this study aims to analyse 25 project characteristics across 28 completed projects, from which three project complexity coefficients are derived. Additionally, a list of risks is defined based on expert evaluations, and the dominant risks are identified. For each of these dominant risks, a prediction model is constructed using Sugeno fuzzy logic, enabling more accurate and sustainable risk management and mitigation in future projects.

Authors

Institutions

Publication Details

Journal
PROMET - Traffic&Transportation
Published
2025-10-27
DOI
https://doi.org/10.7307/ptt.v37i6.1078
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk Prediction in Road Infrastructure Projects Considering Project Complexity Coefficients

Momčilo Đobrodolac, Zoran Stojadinović, Nevena Simić, Aleksandar Senić
PROMET - Traffic&Transportation
Construction Project Management and Performance
article

Risk Prediction in Road Infrastructure Projects Considering Project Complexity Coefficients

Momčilo Đobrodolac, Zoran Stojadinović, Nevena Simić, Aleksandar Senić
article en

Abstract

Risks causing delays in the construction of roads and highways frequently lead to substantial economic and social consequences, with project timelines extending up to three times beyond their initial schedules. These risks not only extend the project timeline but also escalate the overall project execution cost. Despite extensive research on construction-related risks globally, a notable gap remains in studies specifically addressing the risk factors that cause delays in road projects. Analysing completed projects is crucial to derive practical and applicable results, as they offer essential insights into the real-world challenges and risks that may cause timeline extensions and budget escalations. Such an approach ensures that the findings are grounded in actual project outcomes, thereby enhancing their relevance and effectiveness in improving future project planning and risk management. For these reasons, this study aims to analyse 25 project characteristics across 28 completed projects, from which three project complexity coefficients are derived. Additionally, a list of risks is defined based on expert evaluations, and the dominant risks are identified. For each of these dominant risks, a prediction model is constructed using Sugeno fuzzy logic, enabling more accurate and sustainable risk management and mitigation in future projects.

PROMET - Traffic&TransportationVol. 37(6)
University of Belgrade (RS), Saveetha University (IN)
Openalex Percentile: Top 64%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.