Predicting schedule delays of construction projects in the oil and gas industry: comparative study

Purpose Delays in oil and gas construction projects present major challenges due to the sector's complex operations, high capital investment and strict timelines. Such disruptions affect project execution and can have serious socioeconomic impacts. The purpose of this paper is to identify key factors contributing to schedule delays and develop predictive models using artificial neural networks (ANN), decision trees (DTs) and multiple linear regression (MLR) to estimate delay percentages. Design/methodology/approach This study adopts a mixed-methods approach, combining qualitative and quantitative techniques. Expert interviews and a literature review identified and prioritized key delay factors. Data from completed oil and gas construction projects selected through purposive sampling to reflect varied sizes, complexities and locations were analyzed using correlation and outlier tests to ensure reliability. Predictive models: ANNs, DTs and MLR, were then developed, trained and validated with real project data. Findings Design consulting experience, project location and scope changes are assessed as the leading factors influencing delay percentages in oil and gas construction projects. The MLR demonstrated the highest accuracy, exceeding 96%, outperforming both ANNs and DTs. Originality/value This paper focused on the quantitative models rather than the qualitative aspects of predicting schedule delays in construction projects in the oil and gas industry. The proposed models support planning stages by enabling more realistic project schedules and decision-making processes. The proposed models also empower project stakeholders to optimize project outcomes.

Authors

Institutions

Publication Details

Journal
Built Environment Project and Asset Management
Published
2025-10-24
DOI
https://doi.org/10.1108/bepam-12-2024-0286
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Predicting schedule delays of construction projects in the oil and gas industry: comparative study

Awsan Mohammed, Abdullah Alrashidi, Khwaja Mateen Mazher, Ahmed M. Ghaithan et al.
Built Environment Project and Asset Management
Construction Project Management and Performance
article

Predicting schedule delays of construction projects in the oil and gas industry: comparative study

Awsan Mohammed, Abdullah Alrashidi, Khwaja Mateen Mazher, Ahmed M. Ghaithan, Adel Alshibani, Anas Bahatheq
article en

Abstract

Purpose Delays in oil and gas construction projects present major challenges due to the sector's complex operations, high capital investment and strict timelines. Such disruptions affect project execution and can have serious socioeconomic impacts. The purpose of this paper is to identify key factors contributing to schedule delays and develop predictive models using artificial neural networks (ANN), decision trees (DTs) and multiple linear regression (MLR) to estimate delay percentages. Design/methodology/approach This study adopts a mixed-methods approach, combining qualitative and quantitative techniques. Expert interviews and a literature review identified and prioritized key delay factors. Data from completed oil and gas construction projects selected through purposive sampling to reflect varied sizes, complexities and locations were analyzed using correlation and outlier tests to ensure reliability. Predictive models: ANNs, DTs and MLR, were then developed, trained and validated with real project data. Findings Design consulting experience, project location and scope changes are assessed as the leading factors influencing delay percentages in oil and gas construction projects. The MLR demonstrated the highest accuracy, exceeding 96%, outperforming both ANNs and DTs. Originality/value This paper focused on the quantitative models rather than the qualitative aspects of predicting schedule delays in construction projects in the oil and gas industry. The proposed models support planning stages by enabling more realistic project schedules and decision-making processes. The proposed models also empower project stakeholders to optimize project outcomes.

Built Environment Project and Asset ManagementVol. 16(2)
King Fahd University of Petroleum and Minerals (SA)
Openalex Percentile: Top 64%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.