Comparing and extending satisfiability solution methods for the resource-constrained project scheduling problem

This paper solves the resource-constrained project scheduling problem (RCPSP) with a satisfiability problem (SAT) solver. This paper builds further on various existing SAT models for this well-known project scheduling problem and extends them with two methods to satisfy the resource constraints. Specifically, we use the wellknown minimal forbidden sets and compare them with the so-called covers that are traditionally used in SAT implementations. Moreover, we also implement an existing binary decision trees approach under various settings and extend the model with networks with adders, so far never used for solving the RCPSP, to guarantee that resource constraints are satisfied. The algorithms are tested under different settings on a set of 13,413 project instances with diverse network and resource structures, and the experiments demonstrate that a combination of these approaches help in finding better solutions within a reasonable time. Moreover, 393 new lower bounds, 62 new upper bounds, and 290 optimally solved instances (including 18 from the PSPLIB) have been discovered, which, to the best of our knowledge, had not been found before. The strong performance of the new algorithm motivated additional experiments, and the preliminary results suggest several promising directions for future research.

Authors

Publication Details

Journal
Computers & Operations Research
Published
2025-10-20
DOI
https://doi.org/10.1016/j.cor.2025.107308
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Comparing and extending satisfiability solution methods for the resource-constrained project scheduling problem

Mario Vanhoucke, José Coelho
Computers & Operations Research
Resource-Constrained Project Scheduling
article

Comparing and extending satisfiability solution methods for the resource-constrained project scheduling problem

Mario Vanhoucke, José Coelho
article en

Abstract

This paper solves the resource-constrained project scheduling problem (RCPSP) with a satisfiability problem (SAT) solver. This paper builds further on various existing SAT models for this well-known project scheduling problem and extends them with two methods to satisfy the resource constraints. Specifically, we use the wellknown minimal forbidden sets and compare them with the so-called covers that are traditionally used in SAT implementations. Moreover, we also implement an existing binary decision trees approach under various settings and extend the model with networks with adders, so far never used for solving the RCPSP, to guarantee that resource constraints are satisfied. The algorithms are tested under different settings on a set of 13,413 project instances with diverse network and resource structures, and the experiments demonstrate that a combination of these approaches help in finding better solutions within a reasonable time. Moreover, 393 new lower bounds, 62 new upper bounds, and 290 optimally solved instances (including 18 from the PSPLIB) have been discovered, which, to the best of our knowledge, had not been found before. The strong performance of the new algorithm motivated additional experiments, and the preliminary results suggest several promising directions for future research.

Computers & Operations ResearchVol. 186
Openalex Percentile: Top 65%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.