Data-Driven Analysis of Contracting Process Impact on Schedule and Cost Performance in Road Infrastructure Projects in Colombia

This study examines cost and schedule deviations in secondary road infrastructure projects in Colombia, with a focus on the influence of public procurement characteristics. Despite the construction sector’s importance to national development, limited research has explored how procurement-related variables affect project performance. To address this gap, 149 completed road projects were analyzed using data from Colombia’s open procurement database, which provides publicly accessible, standardized information on contracting processes. A four-stage methodology was applied: data collection, exploratory analysis, bivariate analysis (including correlation and Kruskal–Wallis tests), and multivariate analysis using Random Forest and Bayesian networks. Schedule and cost deviations were used as dependent variables, with 17 independent variables. Results show that 81.9% of projects experienced some form of deviation, with a positive correlation between schedule and cost overruns. Significant factors were identified across different stages of the project life cycle. Variables significant for both deviations include the number of bidders, the number of valid bidders, the estimated cost, the final cost, the project intensity, and the type of award process. The findings provide data-driven arguments to improve award processes and support more informed planning of future projects, helping public entities reduce deviations and enhance the outcome of their infrastructure.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2025-10-17
DOI
https://doi.org/10.3390/buildings15203739
Citations
1
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
2.11

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Data-Driven Analysis of Contracting Process Impact on Schedule and Cost Performance in Road Infrastructure Projects in Colombia

Sebastián Pérez, Omar Sánchez, Juan Rojas, Adriana Gómez Cabrera et al.
1 citations
Buildings
Construction Project Management and Performance
2.11
article

Data-Driven Analysis of Contracting Process Impact on Schedule and Cost Performance in Road Infrastructure Projects in Colombia

Sebastián Pérez, Omar Sánchez, Juan Rojas, Adriana Gómez Cabrera, Andrés Torres
article en
1 citations

Abstract

This study examines cost and schedule deviations in secondary road infrastructure projects in Colombia, with a focus on the influence of public procurement characteristics. Despite the construction sector’s importance to national development, limited research has explored how procurement-related variables affect project performance. To address this gap, 149 completed road projects were analyzed using data from Colombia’s open procurement database, which provides publicly accessible, standardized information on contracting processes. A four-stage methodology was applied: data collection, exploratory analysis, bivariate analysis (including correlation and Kruskal–Wallis tests), and multivariate analysis using Random Forest and Bayesian networks. Schedule and cost deviations were used as dependent variables, with 17 independent variables. Results show that 81.9% of projects experienced some form of deviation, with a positive correlation between schedule and cost overruns. Significant factors were identified across different stages of the project life cycle. Variables significant for both deviations include the number of bidders, the number of valid bidders, the estimated cost, the final cost, the project intensity, and the type of award process. The findings provide data-driven arguments to improve award processes and support more informed planning of future projects, helping public entities reduce deviations and enhance the outcome of their infrastructure.

BuildingsVol. 15(20)
Pontificia Universidad Javeriana (CO)
Departamento Administrativo de Ciencia, Tecnología e Innovación (COLCIENCIAS), Pontificia Universidad Javeriana
Openalex Percentile: Top 10%
Construction Project Management and Performance
2.11
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.