A Preliminary Study on the Comparative Schedule Analysis of Traditional and Advanced Work Packaging Plans for Nuclear Power Plant Construction

The construction of nuclear power plants (NPPs) involves complex and long-duration projects where schedule delays critically affect project performance. To overcome this challenge, Advanced Work Packaging (AWP) has emerged as a promising alternative approach. It offers a more integrated and structured way to plan and execute projects, aiming to improve efficiency and reduce the risk of delays. To evaluate the potential benefits, this preliminary study developed and compared a traditional phase-based schedule and two AWP-based schedules. Delay simulations and productivity adjustments were conducted to analyze schedule resilience and mitigation performance. The results show that AWP-based schedules enhance traceability, expand work package granularity, and improve recovery against engineering delays through structured segmentation and Workface Planning (WFP). These findings quantitatively demonstrate the potential of AWP to improve scheduling efficiency not only in NPP projects but also mega construction projects while also identifying gaps in maturity, boundary definition, and integration practices that must be addressed for broader adoption.

Authors

Institutions

Publication Details

Journal
Applied Sciences
Published
2025-10-16
DOI
https://doi.org/10.3390/app152011113
Citations
1
Primary Topic
Technology Assessment and Management
Type
article
Field-Weighted Citation Impact
1.30

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A Preliminary Study on the Comparative Schedule Analysis of Traditional and Advanced Work Packaging Plans for Nuclear Power Plant Construction

Wooyong Jung, Dongwoo Choo
1 citations
Applied Sciences
Technology Assessment and Management
1.30
article

A Preliminary Study on the Comparative Schedule Analysis of Traditional and Advanced Work Packaging Plans for Nuclear Power Plant Construction

Wooyong Jung, Dongwoo Choo
article en
1 citations

Abstract

The construction of nuclear power plants (NPPs) involves complex and long-duration projects where schedule delays critically affect project performance. To overcome this challenge, Advanced Work Packaging (AWP) has emerged as a promising alternative approach. It offers a more integrated and structured way to plan and execute projects, aiming to improve efficiency and reduce the risk of delays. To evaluate the potential benefits, this preliminary study developed and compared a traditional phase-based schedule and two AWP-based schedules. Delay simulations and productivity adjustments were conducted to analyze schedule resilience and mitigation performance. The results show that AWP-based schedules enhance traceability, expand work package granularity, and improve recovery against engineering delays through structured segmentation and Workface Planning (WFP). These findings quantitatively demonstrate the potential of AWP to improve scheduling efficiency not only in NPP projects but also mega construction projects while also identifying gaps in maturity, boundary definition, and integration practices that must be addressed for broader adoption.

Applied SciencesVol. 15(20)
Korea Electric Power Corporation (South Korea) (KR)
Ministry of Land, Infrastructure and Transport, Korea Agency for Infrastructure Technology Advancement, Korea Electric Power Corporation
Openalex Percentile: Top 16%
Technology Assessment and Management
1.30
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.