Enhancing RFI management in construction through machine learning-driven predictive models

Purpose Request for information (RFI) documents are essential for communication and issue resolution in construction projects; however, prolonged RFI resolution times can impact project timelines. This study aims to predict RFI closure durations as they are created and addressed to help identify and prioritize RFIs likely to remain open longer. Design/methodology/approach A dataset of 3,628 RFI documents from a large-scale airport project was used. Five machine learning (ML) algorithms, support vector machine (SVM), logistic regression (LR), K-nearest neighbors (KNN), decision tree (DT) and random forest (RF), were used to create a multi-model prediction framework for RFI closure durations. The models incorporated both categorical metadata and textual data with a staged input structure simulating real project conditions. Findings The most effective algorithms for predicting RFI closure durations were SVM for the model using only RFI metadata parameters as input, and DT when using RFI metadata parameters together with RFI response durations as input. Prediction accuracy improved significantly after using the first response durations, ranging from 59% to 92% for the different models presented. Practical implications Integrated into common data environments, the models enable real-time prediction and prioritization of RFIs, helping teams reduce delays and optimize resources. They also support digital transformation in construction and suggest potential for policy development around predictive analytics in project management. Originality/value This study created prediction models for prioritizing RFIs based on their expected closure durations and identified the most effective ML algorithms for different input variables.

Authors

Institutions

Publication Details

Journal
Smart and Sustainable Built Environment
Published
2025-10-16
DOI
https://doi.org/10.1108/sasbe-05-2025-0254
Citations
1
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
1.01
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Enhancing RFI management in construction through machine learning-driven predictive models

Esin Ergen, Nilay Gul Yilmaz, Ahmet Muhtar Çıtıpıtıoğlu
1 citations
Smart and Sustainable Built Environment
BIM and Construction Integration
1.01
article

Enhancing RFI management in construction through machine learning-driven predictive models

Esin Ergen, Nilay Gul Yilmaz, Ahmet Muhtar Çıtıpıtıoğlu
article en
1 citations

Abstract

Purpose Request for information (RFI) documents are essential for communication and issue resolution in construction projects; however, prolonged RFI resolution times can impact project timelines. This study aims to predict RFI closure durations as they are created and addressed to help identify and prioritize RFIs likely to remain open longer. Design/methodology/approach A dataset of 3,628 RFI documents from a large-scale airport project was used. Five machine learning (ML) algorithms, support vector machine (SVM), logistic regression (LR), K-nearest neighbors (KNN), decision tree (DT) and random forest (RF), were used to create a multi-model prediction framework for RFI closure durations. The models incorporated both categorical metadata and textual data with a staged input structure simulating real project conditions. Findings The most effective algorithms for predicting RFI closure durations were SVM for the model using only RFI metadata parameters as input, and DT when using RFI metadata parameters together with RFI response durations as input. Prediction accuracy improved significantly after using the first response durations, ranging from 59% to 92% for the different models presented. Practical implications Integrated into common data environments, the models enable real-time prediction and prioritization of RFIs, helping teams reduce delays and optimize resources. They also support digital transformation in construction and suggest potential for policy development around predictive analytics in project management. Originality/value This study created prediction models for prioritizing RFIs based on their expected closure durations and identified the most effective ML algorithms for different input variables.

Smart and Sustainable Built Environment
Tashkent Institute of Architecture and Civil Engineering (UZ), Istanbul Technical University (TR)
Openalex Percentile: Top 19%
BIM and Construction Integration
1.01
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.