Hybrid simulation and labor allocation for optimized commercial construction scheduling during COVID-19

Purpose This study develops and validates an integrated simulation framework combining agent-based modeling (ABM), system dynamics (SD) and a modified SEIR epidemiological model to evaluate COVID-19 impacts on commercial construction scheduling and labor allocation. Utilizing empirical data from four construction projects, it examines how varying compliance with safety measures – mask usage, social distancing and vaccination – affects workforce availability, project duration, and costs. The goal is to provide a data-driven decision-support tool for construction managers and policymakers to optimize outcomes and enhance resilience during pandemics. Design/methodology/approach The integrated simulation framework combines ABM, SD and an SEIR model, employing empirical production rates, labor attributes and cost structures from four projects. Workers and tasks are modeled as interactive agents with health status determined by demographic and behavioral factors affecting infection risks. Monte Carlo simulations (n = 1,000) tested varying mask usage, social distancing and vaccination scenarios. Validation involved quantitative metrics (MAPE and RMSE) and expert feedback. Findings Compliance significantly reduced project delays and costs. Noncompliance scenarios increased durations and costs by 9–12%, disproportionately affecting larger sites. High vaccination rates improved workforce stability. Sensitivity analyses highlighted infection probabilities and critical task productivity rates as key performance determinants. Originality/value The study uniquely integrates ABM, SD and epidemiological modeling using real-world data. It offers a robust decision-support framework explicitly addressing the interplay of labor availability, health protocols and construction project outcomes under pandemic-induced uncertainties.

Authors

Institutions

Publication Details

Journal
Engineering Construction & Architectural Management
Published
2025-10-16
DOI
https://doi.org/10.1108/ecam-04-2025-0710
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Hybrid simulation and labor allocation for optimized commercial construction scheduling during COVID-19

Ahmad Al Tarabsheh
Engineering Construction & Architectural Management
BIM and Construction Integration
article

Hybrid simulation and labor allocation for optimized commercial construction scheduling during COVID-19

Ahmad Al Tarabsheh
article en

Abstract

Purpose This study develops and validates an integrated simulation framework combining agent-based modeling (ABM), system dynamics (SD) and a modified SEIR epidemiological model to evaluate COVID-19 impacts on commercial construction scheduling and labor allocation. Utilizing empirical data from four construction projects, it examines how varying compliance with safety measures – mask usage, social distancing and vaccination – affects workforce availability, project duration, and costs. The goal is to provide a data-driven decision-support tool for construction managers and policymakers to optimize outcomes and enhance resilience during pandemics. Design/methodology/approach The integrated simulation framework combines ABM, SD and an SEIR model, employing empirical production rates, labor attributes and cost structures from four projects. Workers and tasks are modeled as interactive agents with health status determined by demographic and behavioral factors affecting infection risks. Monte Carlo simulations (n = 1,000) tested varying mask usage, social distancing and vaccination scenarios. Validation involved quantitative metrics (MAPE and RMSE) and expert feedback. Findings Compliance significantly reduced project delays and costs. Noncompliance scenarios increased durations and costs by 9–12%, disproportionately affecting larger sites. High vaccination rates improved workforce stability. Sensitivity analyses highlighted infection probabilities and critical task productivity rates as key performance determinants. Originality/value The study uniquely integrates ABM, SD and epidemiological modeling using real-world data. It offers a robust decision-support framework explicitly addressing the interplay of labor availability, health protocols and construction project outcomes under pandemic-induced uncertainties.

Engineering Construction & Architectural Management
Al Yarmouk University College (IQ), Yarmouk Private University (SY), Yarmouk University (JO)
Openalex Percentile: Top 68%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.