Evaluation of Scheduling for the Construction of the Jejangkit Bridge Using the Microsoft Project Application Due to Work Delays

The Jejangkit Bridge construction experienced delays due to material shortages and implementation constraints. This study aims to evaluate project scheduling using the Microsoft Project application with the PDM method. Data were sourced from the S-Curve, Contract Quality Plan, and project reports. The results show that the planned project duration was 225 days, while actual implementation reached 240 days due to delays. By applying overtime in key activities, the project could be rescheduled to meet the original timeline.

Authors

Institutions

Publication Details

Journal
East Asian Journal of Multidisciplinary Research
Published
2025-09-15
DOI
https://doi.org/10.55927/eajmr.v4i9.347
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Evaluation of Scheduling for the Construction of the Jejangkit Bridge Using the Microsoft Project Application Due to Work Delays

Fitria Fitria, H. Muhammad Humaidi
East Asian Journal of Multidisciplinary Research
BIM and Construction Integration
article

Evaluation of Scheduling for the Construction of the Jejangkit Bridge Using the Microsoft Project Application Due to Work Delays

Fitria Fitria, H. Muhammad Humaidi
article en

Abstract

The Jejangkit Bridge construction experienced delays due to material shortages and implementation constraints. This study aims to evaluate project scheduling using the Microsoft Project application with the PDM method. Data were sourced from the S-Curve, Contract Quality Plan, and project reports. The results show that the planned project duration was 225 days, while actual implementation reached 240 days due to delays. By applying overtime in key activities, the project could be rescheduled to meet the original timeline.

East Asian Journal of Multidisciplinary ResearchVol. 4(9)
Jakarta State Polytechnic (ID), Politeknik Negeri Banjarmasin
Openalex Percentile: Top 69%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.