Probabilistic generation of topology configurations for reliable expansion planning of distribution grids

The increasing integration of distributed energy resources (DERs) in low voltage grids presents new challenges for distribution system operators (DSOs), such as voltage imbalances and network congestion. To address these challenges, DSOs need to engage in proactive long-term expansion planning. Changes in the switch configuration of the network and lack of documentation contribute to the topology uncertainty in low voltage grids, which must be considered in the planning. To handle the uncertainty, we propose using a set of alternate switch configurations to make the planning process more robust and reliable. Multiple switch states (i.e. topologies) are generated using an efficient Markov Chain Monte Carlo (MCMC) approach and are then jointly analysed to find congestion hotspots. The congestion detection procedure relies on the overload probability of the examined assets (e.g. lines or substations) and on an approach to determine how to achieve the largest number of congestion-free topologies with less interventions. The approach is applied to a real 3032-bus low voltage network in Germany. The results demonstrate that considering multiple topologies can provide valuable insights for long-term planning, instead of using only one topology.

Authors

Institutions

Publication Details

Journal
IET conference proceedings.
Published
2025-10-14
DOI
https://doi.org/10.1049/icp.2025.1937
Primary Topic
Power Systems and Technologies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Probabilistic generation of topology configurations for reliable expansion planning of distribution grids

Michael Metzger, Stefan Niessen, Paul Stursberg, Luiza Voss De Gregorio
IET conference proceedings.
Power Systems and Technologies
article

Probabilistic generation of topology configurations for reliable expansion planning of distribution grids

Michael Metzger, Stefan Niessen, Paul Stursberg, Luiza Voss De Gregorio
article en

Abstract

The increasing integration of distributed energy resources (DERs) in low voltage grids presents new challenges for distribution system operators (DSOs), such as voltage imbalances and network congestion. To address these challenges, DSOs need to engage in proactive long-term expansion planning. Changes in the switch configuration of the network and lack of documentation contribute to the topology uncertainty in low voltage grids, which must be considered in the planning. To handle the uncertainty, we propose using a set of alternate switch configurations to make the planning process more robust and reliable. Multiple switch states (i.e. topologies) are generated using an efficient Markov Chain Monte Carlo (MCMC) approach and are then jointly analysed to find congestion hotspots. The congestion detection procedure relies on the overload probability of the examined assets (e.g. lines or substations) and on an approach to determine how to achieve the largest number of congestion-free topologies with less interventions. The approach is applied to a real 3032-bus low voltage network in Germany. The results demonstrate that considering multiple topologies can provide valuable insights for long-term planning, instead of using only one topology.

IET conference proceedings.Vol. 2025(14)
Siemens (Germany) (DE), Technische Universität Darmstadt (DE)
Openalex Percentile: Top 71%
Power Systems and Technologies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.