Time Delay Risk Analysis in SMPN 2 Mantup Classroom Construction

General Background: Timely completion of construction projects is critical for operational efficiency and cost management. Specific Background: The New Classroom Building Project at SMPN 2 Mantup-Lamongan experienced delays caused by human resources, material availability, and weather conditions, highlighting challenges in project scheduling and risk management. Knowledge Gap: Limited studies provide quantitative assessments of combined environmental, material, and workforce factors on construction delays in local school infrastructure projects. Aims: This study aims to analyze the magnitude of time delays, identify dominant risk factors, and propose mitigation strategies to manage project risks effectively. Results: Data from 45 respondents using questionnaires and analyzed via SPSS revealed that rainfall intensity (21.6%), workforce skill (16.8%), and worker discipline (14.4%) were the leading contributors to delays, with an overall project delay of 6 days compared to the planned schedule. Novelty: The research integrates Critical Path Method calculations with survey-based risk assessment to provide a precise, practical strategy for local construction projects. Implications: Findings offer actionable guidance for contractors and project managers to optimize resource allocation, reduce delays, and improve project reliability. Highlights: Rainfall intensity identified as the highest delay factor. Workforce skill and discipline significantly affect project duration. CPM combined with survey analysis provides actionable mitigation strategies. Keywords: Construction Delays, Risk Analysis, Critical Path, Project Management, SMPN 2 Mantup

Authors

Institutions

Publication Details

Journal
Indonesian Journal of Innovation Studies
Published
2025-09-26
DOI
https://doi.org/10.21070/ijins.v26i4.1752
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Time Delay Risk Analysis in SMPN 2 Mantup Classroom Construction

M. Alvan Rizki, Nola Riwibowo, Wahyu Tri Prambudi, Menik Ariyanti et al.
Indonesian Journal of Innovation Studies
Occupational Health and Safety Management
article

Time Delay Risk Analysis in SMPN 2 Mantup Classroom Construction

M. Alvan Rizki, Nola Riwibowo, Wahyu Tri Prambudi, Menik Ariyanti, Fibia Sentauri Cahyaningrum
article en

Abstract

General Background: Timely completion of construction projects is critical for operational efficiency and cost management. Specific Background: The New Classroom Building Project at SMPN 2 Mantup-Lamongan experienced delays caused by human resources, material availability, and weather conditions, highlighting challenges in project scheduling and risk management. Knowledge Gap: Limited studies provide quantitative assessments of combined environmental, material, and workforce factors on construction delays in local school infrastructure projects. Aims: This study aims to analyze the magnitude of time delays, identify dominant risk factors, and propose mitigation strategies to manage project risks effectively. Results: Data from 45 respondents using questionnaires and analyzed via SPSS revealed that rainfall intensity (21.6%), workforce skill (16.8%), and worker discipline (14.4%) were the leading contributors to delays, with an overall project delay of 6 days compared to the planned schedule. Novelty: The research integrates Critical Path Method calculations with survey-based risk assessment to provide a precise, practical strategy for local construction projects. Implications: Findings offer actionable guidance for contractors and project managers to optimize resource allocation, reduce delays, and improve project reliability. Highlights: Rainfall intensity identified as the highest delay factor. Workforce skill and discipline significantly affect project duration. CPM combined with survey analysis provides actionable mitigation strategies. Keywords: Construction Delays, Risk Analysis, Critical Path, Project Management, SMPN 2 Mantup

Indonesian Journal of Innovation StudiesVol. 26(4)
Institut Teknologi dan Bisnis Kalbe (ID)
Openalex Percentile: Top 58%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.