Studi Teknoekonomi PLTS Apung 141,4 kWp Bendungan Telaga Tunjung Bali

The increasing demand for electrical energy and the issue of climate change are driving the utilization of renewable energy, one of which is through Solar Power Plants (PLTS). The Province of Bali targets the development of PLTS of 108.2 MW, equivalent to 8.62% of the total solar energy potential of 1,254 MW by 2025. However, land limitations pose an obstacle to the construction of large-scale PLTS. Floating solar power plant design can be a solution to this issue. By utilizing 4,955.32 m² of water surface at the Telaga Tunjung Dam, the Floating Solar Power Plant at Telaga Tunjung Dam has a potential capacity of 141.4 kWp, using 280 Trina Solar modules of type TSM-DEG18MC.20(II) (505 Wp) combined with one SG110CX inverter with a capacity of 110 kW. The annual electricity production of the floating solar power plant, based on Helioscope software, is 201.1 MWh. The economic feasibility parameters used in this study include initial investment cost, Profitability Index (PI), and Payback Period (PP). The analysis results show that the 141.4 kWp floating solar power plant project at Telaga Tunjung Dam has an initial investment value of IDR 1,248,764,582, a PI of 1.26, and a PP of 3.91 years. Therefore, this project is considered economically feasible and contributes positively to reducing CO₂ emissions.

Authors

Institutions

Publication Details

Journal
JURAL RISET RUMPUN ILMU TEKNIK
Published
2025-10-14
DOI
https://doi.org/10.55606/jurritek.v4i3.6893
Primary Topic
Fluid dynamics and aerodynamics studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Studi Teknoekonomi PLTS Apung 141,4 kWp Bendungan Telaga Tunjung Bali

I Wayan Sukerayasa, Wayan Gede Ariastina, I Nyoman Satya Kumara, Julius Mahendra Sihombing et al.
JURAL RISET RUMPUN ILMU TEKNIK
Fluid dynamics and aerodynamics studies
article

Studi Teknoekonomi PLTS Apung 141,4 kWp Bendungan Telaga Tunjung Bali

I Wayan Sukerayasa, Wayan Gede Ariastina, I Nyoman Satya Kumara, Julius Mahendra Sihombing, Surung Rafael Sihaloho
article en

Abstract

The increasing demand for electrical energy and the issue of climate change are driving the utilization of renewable energy, one of which is through Solar Power Plants (PLTS). The Province of Bali targets the development of PLTS of 108.2 MW, equivalent to 8.62% of the total solar energy potential of 1,254 MW by 2025. However, land limitations pose an obstacle to the construction of large-scale PLTS. Floating solar power plant design can be a solution to this issue. By utilizing 4,955.32 m² of water surface at the Telaga Tunjung Dam, the Floating Solar Power Plant at Telaga Tunjung Dam has a potential capacity of 141.4 kWp, using 280 Trina Solar modules of type TSM-DEG18MC.20(II) (505 Wp) combined with one SG110CX inverter with a capacity of 110 kW. The annual electricity production of the floating solar power plant, based on Helioscope software, is 201.1 MWh. The economic feasibility parameters used in this study include initial investment cost, Profitability Index (PI), and Payback Period (PP). The analysis results show that the 141.4 kWp floating solar power plant project at Telaga Tunjung Dam has an initial investment value of IDR 1,248,764,582, a PI of 1.26, and a PP of 3.91 years. Therefore, this project is considered economically feasible and contributes positively to reducing CO₂ emissions.

JURAL RISET RUMPUN ILMU TEKNIKVol. 4(3)
Udayana University (ID)
Openalex Percentile: Top 69%
Fluid dynamics and aerodynamics studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.