Load Shedding Analysis using Under Frequency Relay (UFR) at Bolangi Substation using ETAP Software

This study aims to analyze the performance of the load shedding system using Under Frequency Relay (UFR) at the Bolangi Substation as an effort to maintain the stability of the power system frequency. A supply disruption from Bayline Daya Baru (#2) occurred, namely a disturbance due to a lightning strike, which is an important background in this study. A decrease in frequency due to power imbalance can cause a total power outage (blackout), so a responsive UFR protection system is needed. Simulations were carried out using ETAP 19.0 software with a bayline release scenario to analyze the frequency response and effectiveness of automatic load shedding. The simulation results show that a frequency decrease of up to 48.60 Hz can be restored to 50 Hz in 2.47 seconds through gradual load shedding of 13.34 MW by UFR stages 2 and 4. This study provides an overview of the load shedding stages based on the frequency setting values ​​and periodic UFR working times as well as the use of ETAP for continuous evaluation of the protection system at the substation.

Authors

Institutions

Publication Details

Journal
Journal of Renewable Energy and Smart Device
Published
2025-10-13
DOI
https://doi.org/10.61220/joresd.v3i1.253
Primary Topic
Power Systems and Technologies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Load Shedding Analysis using Under Frequency Relay (UFR) at Bolangi Substation using ETAP Software

Zulhajji Zulhajji, Yunus Tjandi, Muh. Iswal Burhan, Rezky Ramadhani
Journal of Renewable Energy and Smart Device
Power Systems and Technologies
article

Load Shedding Analysis using Under Frequency Relay (UFR) at Bolangi Substation using ETAP Software

Zulhajji Zulhajji, Yunus Tjandi, Muh. Iswal Burhan, Rezky Ramadhani
article en

Abstract

This study aims to analyze the performance of the load shedding system using Under Frequency Relay (UFR) at the Bolangi Substation as an effort to maintain the stability of the power system frequency. A supply disruption from Bayline Daya Baru (#2) occurred, namely a disturbance due to a lightning strike, which is an important background in this study. A decrease in frequency due to power imbalance can cause a total power outage (blackout), so a responsive UFR protection system is needed. Simulations were carried out using ETAP 19.0 software with a bayline release scenario to analyze the frequency response and effectiveness of automatic load shedding. The simulation results show that a frequency decrease of up to 48.60 Hz can be restored to 50 Hz in 2.47 seconds through gradual load shedding of 13.34 MW by UFR stages 2 and 4. This study provides an overview of the load shedding stages based on the frequency setting values ​​and periodic UFR working times as well as the use of ETAP for continuous evaluation of the protection system at the substation.

Journal of Renewable Energy and Smart Device
State University of Makassar (ID)
Openalex Percentile: Top 72%
Power Systems and Technologies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.