Risk Management in the PPP Scheme for the East Sumatra National Ring Road Preservation Project in Riau Province

The East Sumatra Highway, particularly the Pekanbaru–Simpang Lago section in Pelalawan Regency, is a strategic route that supports national economic growth and is part of the National Road network, which experiences congestion due to heavily loaded vehicles. As the need for road infrastructure intensifies, the government faces limitations in the State Revenue and Expenditure Budget (APBN). Therefore, alternative financing mechanisms such as State Sharia Securities (SBSN) and the Government and Business Entity Cooperation (PPP) scheme are required. This study aims to identify and assess the risks in the East Sumatra National Road Preservation PPP Project using a type-1 questionnaire-based descriptive analysis approach. The research respondents consist of representatives from the Party in Charge of the Cooperation Project (PJPK) and the Implementing Business Entity (BUP). The results indicate that PJPK faces 63 risks, with the main classifications including location, design, construction, operations, revenue, political, financial, force majeure, sponsorship, interface, asset ownership, and strategy. Meanwhile, BUP faces 60 risks under similar classifications, except that location risks fall solely under the responsibility of PJPK. These findings highlight the importance of proportional risk sharing according to the authority and responsibilities of each party. This research contributes to the development of risk mitigation strategies and supports decision-making for PPP-based infrastructure project financing. For future research, the use of the fuzzy logic method is recommended to reinforce risk weight allocation and to broaden the respondent base from both parties, thereby producing more representative results.

Authors

Institutions

Publication Details

Journal
Enrichment Journal of Multidisciplinary Research and Development
Published
2025-10-09
DOI
https://doi.org/10.55324/enrichment.v3i7.478
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk Management in the PPP Scheme for the East Sumatra National Ring Road Preservation Project in Riau Province

Hari Nugraha Nurjaman, Arman Jayady, Munarlis Papua
Enrichment Journal of Multidisciplinary Research and Development
Occupational Health and Safety Management
article

Risk Management in the PPP Scheme for the East Sumatra National Ring Road Preservation Project in Riau Province

Hari Nugraha Nurjaman, Arman Jayady, Munarlis Papua
article en

Abstract

The East Sumatra Highway, particularly the Pekanbaru–Simpang Lago section in Pelalawan Regency, is a strategic route that supports national economic growth and is part of the National Road network, which experiences congestion due to heavily loaded vehicles. As the need for road infrastructure intensifies, the government faces limitations in the State Revenue and Expenditure Budget (APBN). Therefore, alternative financing mechanisms such as State Sharia Securities (SBSN) and the Government and Business Entity Cooperation (PPP) scheme are required. This study aims to identify and assess the risks in the East Sumatra National Road Preservation PPP Project using a type-1 questionnaire-based descriptive analysis approach. The research respondents consist of representatives from the Party in Charge of the Cooperation Project (PJPK) and the Implementing Business Entity (BUP). The results indicate that PJPK faces 63 risks, with the main classifications including location, design, construction, operations, revenue, political, financial, force majeure, sponsorship, interface, asset ownership, and strategy. Meanwhile, BUP faces 60 risks under similar classifications, except that location risks fall solely under the responsibility of PJPK. These findings highlight the importance of proportional risk sharing according to the authority and responsibilities of each party. This research contributes to the development of risk mitigation strategies and supports decision-making for PPP-based infrastructure project financing. For future research, the use of the fuzzy logic method is recommended to reinforce risk weight allocation and to broaden the respondent base from both parties, thereby producing more representative results.

Enrichment Journal of Multidisciplinary Research and DevelopmentVol. 3(7)
Universitas Persada Indonesia Yayasan Administrasi Indonesia (ID)
Openalex Percentile: Top 58%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.