A Study on Construction Schedule Management Methods under Disruptive Conditions Based on Combinatorial Thinking

Abstract With the increasing frequency of disruptions in construction projects, the traditional Critical Path Method (CPM) shows limitations in handling schedule disturbances due to its static structure and inflexible adjustment mechanisms. This paper proposes a schedule sensitivity assessment method under disruptive conditions, based on a combinatorial thinking model. By representing the project network with matrices and scanning multi-task combinations, we introduce two indices-Schedule Sensitivity Index (SSI) and Cost Sensitivity Index (CSI)-to quantify how combinations of tasks affect overall project objectives under different disturbance scenarios. A simulated case based on a construction project is used to illustrate the approach. For example, under combined schedule-cost variation, the AGF task group induces the greatest schedule delay, while the ILM group exhibits the lowest overall sensitivity. The proposed method indicates potential to support decision-making in resource allocation and may improve adaptability the adaptability of construction schedule management under uncertain and dynamic conditions.

Authors

Institutions

Publication Details

Journal
Civil and Environmental Engineering
Published
2025-10-08
DOI
https://doi.org/10.2478/cee-2026-0016
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A Study on Construction Schedule Management Methods under Disruptive Conditions Based on Combinatorial Thinking

Zhengfeng Ma, Hsu‐Hao Yang, Yang Chen, Jingyi Chen et al.
Civil and Environmental Engineering
BIM and Construction Integration
article

A Study on Construction Schedule Management Methods under Disruptive Conditions Based on Combinatorial Thinking

Zhengfeng Ma, Hsu‐Hao Yang, Yang Chen, Jingyi Chen, Junwu Xiong
article en

Abstract

Abstract With the increasing frequency of disruptions in construction projects, the traditional Critical Path Method (CPM) shows limitations in handling schedule disturbances due to its static structure and inflexible adjustment mechanisms. This paper proposes a schedule sensitivity assessment method under disruptive conditions, based on a combinatorial thinking model. By representing the project network with matrices and scanning multi-task combinations, we introduce two indices-Schedule Sensitivity Index (SSI) and Cost Sensitivity Index (CSI)-to quantify how combinations of tasks affect overall project objectives under different disturbance scenarios. A simulated case based on a construction project is used to illustrate the approach. For example, under combined schedule-cost variation, the AGF task group induces the greatest schedule delay, while the ILM group exhibits the lowest overall sensitivity. The proposed method indicates potential to support decision-making in resource allocation and may improve adaptability the adaptability of construction schedule management under uncertain and dynamic conditions.

Civil and Environmental EngineeringVol. 22(1)
Qinghai University (CN), Chongqing Jiaotong University (CN)
Openalex Percentile: Top 70%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

A Study on Construction Schedule Management Methods under Disruptive Conditions Based on Combinatorial Thinking — Zhengfeng Ma, Hsu‐Hao Yang, et al. · Civil and Environmental Engineering (2025) | TGRS Research Map | TGRS