FACTORS CAUSING DELAYS IN THE CONSTRUCTION INDUSTRY IN THE CITY OF AL-ABYAR, LIBYA

This study focuses on determining the factors contributing to project delay in general and identified the top ten factors that lead delays in in the city of Al-Abyar, Libya. Date was collected through questionnaire survey, 73 questionnaires were sent out to project managers, contractors and consultants in the above-mentioned city, of these only 62 completed questionnaires were returned and analyzed, yielding a response rate 85%. As results, these factors are lack of skilled labour, poor communication and coordination, contractor’s poor site management, mistakes during the construction stage, equipment availability and failure and problems with subcontractors. Several strategies to mitigate these factors were recommends, such as providing regular meetings and clear communication channels can achieve effective communication and coordination. These recommendations can provide practical insights for practitioners and policymakers in the construction industry to mitigate the impact of cost overruns and delays.

Authors

Publication Details

Journal
NOON Scientific Journal
Published
2025-06-30
DOI
https://doi.org/10.64587/nsjapgsagaa
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

FACTORS CAUSING DELAYS IN THE CONSTRUCTION INDUSTRY IN THE CITY OF AL-ABYAR, LIBYA

ABDELWAHAB OMRAN GEBRIL, ABDULKARIM EMRAN JIBREEL ALI
NOON Scientific Journal
Construction Project Management and Performance
article

FACTORS CAUSING DELAYS IN THE CONSTRUCTION INDUSTRY IN THE CITY OF AL-ABYAR, LIBYA

ABDELWAHAB OMRAN GEBRIL, ABDULKARIM EMRAN JIBREEL ALI
article en

Abstract

This study focuses on determining the factors contributing to project delay in general and identified the top ten factors that lead delays in in the city of Al-Abyar, Libya. Date was collected through questionnaire survey, 73 questionnaires were sent out to project managers, contractors and consultants in the above-mentioned city, of these only 62 completed questionnaires were returned and analyzed, yielding a response rate 85%. As results, these factors are lack of skilled labour, poor communication and coordination, contractor’s poor site management, mistakes during the construction stage, equipment availability and failure and problems with subcontractors. Several strategies to mitigate these factors were recommends, such as providing regular meetings and clear communication channels can achieve effective communication and coordination. These recommendations can provide practical insights for practitioners and policymakers in the construction industry to mitigate the impact of cost overruns and delays.

NOON Scientific Journal
Openalex Percentile: Top 67%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.