Analysis of the Quality, Time, and Cost Planning of the Space Frame Steel Roof Structure in the Indonesia Arena GBK Stadium Project in Jakarta

The Indonesia Arena GBK Stadium in Jakarta is the first international-standard indoor stadium in Indonesia with a capacity of approximately 16,000 spectators and a roof span of 130 × 103 m. This study analyzes the quality, cost, and installation time of the space frame roof structure and provides optimization recommendations for similar projects. The results show that quality is maintained through systematic work methods, effective zoning, and continuous quality control. The implementation cost was recorded at IDR 57.57 billion with a duration of 105 days for 27 zones. Optimization is recommended through digital inspection, on-ground module prefabrication, parallel work between zones, and integrated material procurement. Space frame technology has been proven to increase installation efficiency and minimize delays, so that the project is completed on time for the 2023 FIBA World Cup.

Authors

Publication Details

Journal
Jurnal Ilmiah Teknik
Published
2025-09-18
DOI
https://doi.org/10.56127/juit.v4i3.2284
Primary Topic
Structural Engineering and Vibration Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of the Quality, Time, and Cost Planning of the Space Frame Steel Roof Structure in the Indonesia Arena GBK Stadium Project in Jakarta

M R H Kamil, Alizar Alizar
Jurnal Ilmiah Teknik
Structural Engineering and Vibration Analysis
article

Analysis of the Quality, Time, and Cost Planning of the Space Frame Steel Roof Structure in the Indonesia Arena GBK Stadium Project in Jakarta

M R H Kamil, Alizar Alizar
article en

Abstract

The Indonesia Arena GBK Stadium in Jakarta is the first international-standard indoor stadium in Indonesia with a capacity of approximately 16,000 spectators and a roof span of 130 × 103 m. This study analyzes the quality, cost, and installation time of the space frame roof structure and provides optimization recommendations for similar projects. The results show that quality is maintained through systematic work methods, effective zoning, and continuous quality control. The implementation cost was recorded at IDR 57.57 billion with a duration of 105 days for 27 zones. Optimization is recommended through digital inspection, on-ground module prefabrication, parallel work between zones, and integrated material procurement. Space frame technology has been proven to increase installation efficiency and minimize delays, so that the project is completed on time for the 2023 FIBA World Cup.

Jurnal Ilmiah TeknikVol. 4(3)
Openalex Percentile: Top 71%
Structural Engineering and Vibration Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.