Analysis of Delay Factors in the Capital Expenditure Package and Public Facilities Project of Turyapada Tower Technology Park KBS 6.0 Kerthi Bali

Delays in construction projects often impact cost, time, and quality. This study was conducted on the Turyapada Tower Technology Park KBS 6.0 Kerthi Bali project, which experienced delays from its initial schedule. The aim of the research is to identify and analyze the dominant factors contributing to project delays. Using a quantitative method through questionnaires distributed to 50 respondents and data analysis with validity tests, reliability tests, and Pearson correlation in SPSS, the results indicate that environmental and equipment factors are the primary causes of delays, followed by labor, management, execution methods, and materials. The dominant factors show a very strong correlation with project schedule delays. These findings are expected to serve as an evaluation and input to improve timeliness and efficiency in similar projects in the future.

Authors

Publication Details

Journal
Jurnal Ilmiah Teknik
Published
2025-09-16
DOI
https://doi.org/10.56127/juit.v4i3.2287
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Delay Factors in the Capital Expenditure Package and Public Facilities Project of Turyapada Tower Technology Park KBS 6.0 Kerthi Bali

Rizal Adi Saputra, R Sitorus
Jurnal Ilmiah Teknik
Occupational Health and Safety Management
article

Analysis of Delay Factors in the Capital Expenditure Package and Public Facilities Project of Turyapada Tower Technology Park KBS 6.0 Kerthi Bali

Rizal Adi Saputra, R Sitorus
article en

Abstract

Delays in construction projects often impact cost, time, and quality. This study was conducted on the Turyapada Tower Technology Park KBS 6.0 Kerthi Bali project, which experienced delays from its initial schedule. The aim of the research is to identify and analyze the dominant factors contributing to project delays. Using a quantitative method through questionnaires distributed to 50 respondents and data analysis with validity tests, reliability tests, and Pearson correlation in SPSS, the results indicate that environmental and equipment factors are the primary causes of delays, followed by labor, management, execution methods, and materials. The dominant factors show a very strong correlation with project schedule delays. These findings are expected to serve as an evaluation and input to improve timeliness and efficiency in similar projects in the future.

Jurnal Ilmiah TeknikVol. 4(3)
Openalex Percentile: Top 59%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.