Tender simulation using the Friedman method in factory buildings project

Winning a project tender with a large profit and a low bid value is an obstacle for the contractor. An accuracy level of 5% to 10% in cost estimates is required when preparing bids; to overcome this, markup analysis is needed to increase the probability of winning and profit according to expectations. The methods used to find the appropriate probability of winning and expected profit are the Friedman method. The results of this research in the case study of the project PT. XYZ, three contractors took part in the tender and were given the symbol PT. C1, PT. C2, and PT. C3. The results of the data analysis of the probability of winning the tender for the construction project work between PT. C1, PT. C2, and PT. C3 shows that PT. C1 has a 97.90% probability of winning using the Friedman method. The highest profit amount using the Friedman method, and in line with expectations, when participating in the tender for construction project work between PT. C1, PT. C2, and PT. C3 is PT C1with profit 13.22%.

Publication Details

Journal
ARPN Journal of Engineering and Applied Sciences
Published
2025-09-15
DOI
https://doi.org/10.59018/0625104
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Tender simulation using the Friedman method in factory buildings project

ARPN Journal of Engineering and Applied Sciences
BIM and Construction Integration
article

Tender simulation using the Friedman method in factory buildings project

article en

Abstract

Winning a project tender with a large profit and a low bid value is an obstacle for the contractor. An accuracy level of 5% to 10% in cost estimates is required when preparing bids; to overcome this, markup analysis is needed to increase the probability of winning and profit according to expectations. The methods used to find the appropriate probability of winning and expected profit are the Friedman method. The results of this research in the case study of the project PT. XYZ, three contractors took part in the tender and were given the symbol PT. C1, PT. C2, and PT. C3. The results of the data analysis of the probability of winning the tender for the construction project work between PT. C1, PT. C2, and PT. C3 shows that PT. C1 has a 97.90% probability of winning using the Friedman method. The highest profit amount using the Friedman method, and in line with expectations, when participating in the tender for construction project work between PT. C1, PT. C2, and PT. C3 is PT C1with profit 13.22%.

ARPN Journal of Engineering and Applied Sciences
Openalex Percentile: Top 70%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.