Integrated Bayesian-Monte Carlo Based Probabilistic Risk Modeling of Cost Overruns in Infrastructure Projects

Cost overruns in road construction projects significantly challenge project efficiency and financial sustainability. This study develops an integrated Bayesian-Monte Carlo framework to identify and quantify critical cost overrun factors in Pakistan's road infrastructure projects. Through literature review and expert consultation, 25 potential causes were systematically reduced to 10 critical factors using expert elicitation and criticality scoring. Bayesian analysis calculated posterior probabilities by combining expert judgment with conditional relationships, while Monte Carlo simulation quantified uncertainties and provided probabilistic ranges for each factor. The framework reveals design error changes as the most critical factor (mean: 61.5%, maximum: 93.3%), followed by variation orders (58.9%) and inaccurate estimates (57.8%). Secondary contributors include land acquisition issues (54.5%) and schedule delays (52.3%). This integrated approach enables evidence-based risk prioritization, replacing arbitrary contingency planning with data-driven decision making. The methodology provides project managers with actionable insights for targeted risk mitigation and optimal resource allocation in resource-constrained environments.

Authors

Institutions

Publication Details

Journal
Fusion Journal of Engineering and Sciences
Published
2025-10-04
DOI
https://doi.org/10.64615/fjes.1.specialissue.2025.29
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Integrated Bayesian-Monte Carlo Based Probabilistic Risk Modeling of Cost Overruns in Infrastructure Projects

Muhammad Usman Hassan, Hilal Musadiq Khan, Khursheed Ahmed
Fusion Journal of Engineering and Sciences
Construction Project Management and Performance
article

Integrated Bayesian-Monte Carlo Based Probabilistic Risk Modeling of Cost Overruns in Infrastructure Projects

Muhammad Usman Hassan, Hilal Musadiq Khan, Khursheed Ahmed
article en

Abstract

Cost overruns in road construction projects significantly challenge project efficiency and financial sustainability. This study develops an integrated Bayesian-Monte Carlo framework to identify and quantify critical cost overrun factors in Pakistan's road infrastructure projects. Through literature review and expert consultation, 25 potential causes were systematically reduced to 10 critical factors using expert elicitation and criticality scoring. Bayesian analysis calculated posterior probabilities by combining expert judgment with conditional relationships, while Monte Carlo simulation quantified uncertainties and provided probabilistic ranges for each factor. The framework reveals design error changes as the most critical factor (mean: 61.5%, maximum: 93.3%), followed by variation orders (58.9%) and inaccurate estimates (57.8%). Secondary contributors include land acquisition issues (54.5%) and schedule delays (52.3%). This integrated approach enables evidence-based risk prioritization, replacing arbitrary contingency planning with data-driven decision making. The methodology provides project managers with actionable insights for targeted risk mitigation and optimal resource allocation in resource-constrained environments.

Fusion Journal of Engineering and Sciences
National University of Sciences and Technology (PK)
Openalex Percentile: Top 68%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Integrated Bayesian-Monte Carlo Based Probabilistic Risk Modeling of Cost Overruns in Infrastructure Projects — Muhammad Usman Hassan, Hilal Musadiq Khan, et al. · Fusion Journal of Engineering and Sciences (2025) | TGRS Research Map | TGRS