Development of Risk Assessment Model for Controlling Cost Overrun in Road Maintenance Projects: A Case of Roads in Songea District, Tanzania

This study was designed to develop a risk assessment model for controlling cost overruns in road maintenance projects, using roads in Songea District as a case study. It addressed the persistent problem of financial inefficiencies and unexpected cost escalations that frequently undermine the success of infrastructure maintenance in Tanzania. The study sought to systematically identify the key risk factors contributing to cost overruns and establish a model to predict and mitigate these risks in future projects. The research was motivated by the critical role of road infrastructure in economic development and the increasing challenges faced by agencies like TARURA and TANROADS in managing project budgets amidst growing demand and environmental volatility. Employing a quantitative research design, the study used structured questionnaires to collect data on six major risk categories: financial risks, environmental and climatic risks, project management risks, stakeholder risks, maintenance method risks, and resource-related risks. Multiple linear regression analysis was used to quantify their relationship with cost overrun, and model validation was conducted using five years of historical data from TARURA. The findings revealed that financial and environmental risks exert the greatest influence on cost overruns, followed by project management and resource-related risks, while maintenance methods and stakeholder concerns had minimal influence. The developed model demonstrated consistent performance, showing that approximately 22.71% of cost overruns could be mitigated through its application. The study concludes that integrating risk assessment models into road maintenance planning can significantly enhance budget control, promote infrastructure sustainability, and improve strategic decision-making

Authors

Publication Details

Journal
International Journal of Advanced Research
Published
2025-10-04
DOI
https://doi.org/10.37284/ijar.8.2.3759
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Development of Risk Assessment Model for Controlling Cost Overrun in Road Maintenance Projects: A Case of Roads in Songea District, Tanzania

Jubily Musagasa, Joseph Mkilania, Godfrey Cliford Mngale
International Journal of Advanced Research
Construction Project Management and Performance
article

Development of Risk Assessment Model for Controlling Cost Overrun in Road Maintenance Projects: A Case of Roads in Songea District, Tanzania

Jubily Musagasa, Joseph Mkilania, Godfrey Cliford Mngale
article en

Abstract

This study was designed to develop a risk assessment model for controlling cost overruns in road maintenance projects, using roads in Songea District as a case study. It addressed the persistent problem of financial inefficiencies and unexpected cost escalations that frequently undermine the success of infrastructure maintenance in Tanzania. The study sought to systematically identify the key risk factors contributing to cost overruns and establish a model to predict and mitigate these risks in future projects. The research was motivated by the critical role of road infrastructure in economic development and the increasing challenges faced by agencies like TARURA and TANROADS in managing project budgets amidst growing demand and environmental volatility. Employing a quantitative research design, the study used structured questionnaires to collect data on six major risk categories: financial risks, environmental and climatic risks, project management risks, stakeholder risks, maintenance method risks, and resource-related risks. Multiple linear regression analysis was used to quantify their relationship with cost overrun, and model validation was conducted using five years of historical data from TARURA. The findings revealed that financial and environmental risks exert the greatest influence on cost overruns, followed by project management and resource-related risks, while maintenance methods and stakeholder concerns had minimal influence. The developed model demonstrated consistent performance, showing that approximately 22.71% of cost overruns could be mitigated through its application. The study concludes that integrating risk assessment models into road maintenance planning can significantly enhance budget control, promote infrastructure sustainability, and improve strategic decision-making

International Journal of Advanced ResearchVol. 8(2)
Openalex Percentile: Top 68%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Development of Risk Assessment Model for Controlling Cost Overrun in Road Maintenance Projects: A Case of Roads in Songea District, Tanzania — Jubily Musagasa, Joseph Mkilania, et al. · International Journal of Advanced Research (2025) | TGRS Research Map | TGRS