Automatic mapping of schedule activities and reality models for tracking construction progress

Purpose The purpose of this research is to develop a novel method for automatically aligning schedule activities with reality models to track construction project progress. This approach aims to overcome the limitations of traditional methods that depend on 4D Building Information Models (BIM), which are often labor-intensive to create and can quickly become outdated. Design/methodology/approach The proposed methodology utilizes visual data to monitor construction progress. It employs 3D BIM or ground control points to align reality models and utilizes point cloud segmentation and image segmentation for progress detection. Natural language processing (NLP) is used to extract location, object and task information from schedule activities. A distance-based matching technique is applied to map reality model components with the corresponding scheduled activities. The method is tested on two building construction projects: one with a 3D BIM and another without. Findings The testing on two case studies demonstrated the method’s capability to automatically track construction progress by accurately aligning schedule activities with reality models, even in the absence of an up-to-date 4D BIM. The approach showed significant potential in streamlining progress monitoring processes, enhancing accuracy and reducing the need for manual updates, thereby supporting more effective project management and decision-making. Originality/value This research presents a novel integration of NLP, point cloud segmentation and image segmentation for construction progress monitoring, offering a unique solution that bypasses the need for a current 4D BIM. The approach addresses key industry challenges by automating the alignment of schedule activities with reality models, providing a valuable tool for enhancing the efficiency and accuracy of project progress tracking in construction management.

Authors

Institutions

Publication Details

Journal
Engineering Construction & Architectural Management
Published
2025-09-26
DOI
https://doi.org/10.1108/ecam-08-2024-1166
Citations
3
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
3.02
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Automatic mapping of schedule activities and reality models for tracking construction progress

Shang‐Hsien Hsieh, Jacob J. Lin, Aritra Pal, Fouad Amer et al.
3 citations
Engineering Construction & Architectural Management
BIM and Construction Integration
3.02
article

Automatic mapping of schedule activities and reality models for tracking construction progress

Shang‐Hsien Hsieh, Jacob J. Lin, Aritra Pal, Fouad Amer, Mani Golparvar Fard
article en
3 citations

Abstract

Purpose The purpose of this research is to develop a novel method for automatically aligning schedule activities with reality models to track construction project progress. This approach aims to overcome the limitations of traditional methods that depend on 4D Building Information Models (BIM), which are often labor-intensive to create and can quickly become outdated. Design/methodology/approach The proposed methodology utilizes visual data to monitor construction progress. It employs 3D BIM or ground control points to align reality models and utilizes point cloud segmentation and image segmentation for progress detection. Natural language processing (NLP) is used to extract location, object and task information from schedule activities. A distance-based matching technique is applied to map reality model components with the corresponding scheduled activities. The method is tested on two building construction projects: one with a 3D BIM and another without. Findings The testing on two case studies demonstrated the method’s capability to automatically track construction progress by accurately aligning schedule activities with reality models, even in the absence of an up-to-date 4D BIM. The approach showed significant potential in streamlining progress monitoring processes, enhancing accuracy and reducing the need for manual updates, thereby supporting more effective project management and decision-making. Originality/value This research presents a novel integration of NLP, point cloud segmentation and image segmentation for construction progress monitoring, offering a unique solution that bypasses the need for a current 4D BIM. The approach addresses key industry challenges by automating the alignment of schedule activities with reality models, providing a valuable tool for enhancing the efficiency and accuracy of project progress tracking in construction management.

Engineering Construction & Architectural ManagementVol. 33(3)
University of Illinois Urbana-Champaign (US), National Taiwan University (TW), Indian Institute of Technology Madras (IN)
Openalex Percentile: Top 9%
BIM and Construction Integration
3.02
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.