Roadmap for Implementing Standardized Work in Construction Process with Takt Time Planning

Lack of predictability, high workforce turnover, and making-do are some of the factors that contribute to process variability in construction.Variability can disrupt workflow, negatively impacting the performance of production systems in terms of cost, duration, and project quality.Standardized Work (SW) is an approach from the Lean Production Philosophy that enhances process stability by establishing procedures that standardize each worker's tasks.However, despite its widespread application in the manufacturing industry, the full potential of this approach remains underutilized in construction.This paper presents the results of implementing SW in the concrete structure process of a residential project undertaken by a Chilean company.The study adapts the key elements of SW to the construction context and engages workers in defining a standard routine.Action research is the methodological approach adopted in this study.The results show that SW, along with interventions supporting continuous improvement, reduces operational variability, enhances workspace organization, and increases workers' selfmanagement in meeting their goals.This approach improves the operational efficiency of construction projects and contributes to a broader understanding of effective strategies for managing process variability in construction.

Authors

Publication Details

Journal
Annual Conference of the International Group for Lean Construction
Published
2025-06-02
DOI
https://doi.org/10.24928/2025/0133
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Roadmap for Implementing Standardized Work in Construction Process with Takt Time Planning

N. Orellana, Marcus P. Sterzi, R. Villanueva, Karina B. Barth et al.
Annual Conference of the International Group for Lean Construction
BIM and Construction Integration
article

Roadmap for Implementing Standardized Work in Construction Process with Takt Time Planning

N. Orellana, Marcus P. Sterzi, R. Villanueva, Karina B. Barth, Fabiana Bonesi
article en

Abstract

Lack of predictability, high workforce turnover, and making-do are some of the factors that contribute to process variability in construction.Variability can disrupt workflow, negatively impacting the performance of production systems in terms of cost, duration, and project quality.Standardized Work (SW) is an approach from the Lean Production Philosophy that enhances process stability by establishing procedures that standardize each worker's tasks.However, despite its widespread application in the manufacturing industry, the full potential of this approach remains underutilized in construction.This paper presents the results of implementing SW in the concrete structure process of a residential project undertaken by a Chilean company.The study adapts the key elements of SW to the construction context and engages workers in defining a standard routine.Action research is the methodological approach adopted in this study.The results show that SW, along with interventions supporting continuous improvement, reduces operational variability, enhances workspace organization, and increases workers' selfmanagement in meeting their goals.This approach improves the operational efficiency of construction projects and contributes to a broader understanding of effective strategies for managing process variability in construction.

Annual Conference of the International Group for Lean Construction
Openalex Percentile: Top 74%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Roadmap for Implementing Standardized Work in Construction Process with Takt Time Planning — N. Orellana, Marcus P. Sterzi, et al. · Annual Conference of the International Group for Lean Construction (2025) | TGRS Research Map | TGRS