What are the Main Causes of Discontinuous Work?

Discontinuous work in construction refers to periods without resource or work continuity, leaving workers without designated locations to perform their tasks.Studies show in many activities idle durations are a significant portion of total work.Caused by poor production system design in projects, discontinuous work is a major cause of low trade productivity.This paper aims to identify factors affecting discontinuous work and quantify their impact.346 datapoints (including 46 superstructure crews across 75 building levels in 10 multistorey buildings in London) were analysed using correlation and regression techniques.Data included crew size, batch size, activity type, work start and end dates.Results showed that reducing the batch size by increasing slab concrete pours per level minimised discontinuities by ensuring more available work locations.Synchronising the production rates of successive crews also reduced discontinuities by limiting idle time for faster crews.Surprisingly, although often considered a cause of discontinuities, out-of-sequence work had no statistically significant relationship with discontinuities.Possibly due to the constraints of superstructure work limiting the out-of-sequence work.Additionally, offsite construction methods exhibited greater variability in discontinuities compared to in-situ methods, likely due to clashes between in-situ activities happening at a different rate of work to offsite activities.

Authors

Publication Details

Journal
Annual Conference of the International Group for Lean Construction
Published
2025-06-02
DOI
https://doi.org/10.24928/2025/0129
Primary Topic
Digital Economy and Work Transformation
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

What are the Main Causes of Discontinuous Work?

Danny Murguía, A.K. Pal, Ashan Senel Asmone, Asitha Rathnayake et al.
Annual Conference of the International Group for Lean Construction
Digital Economy and Work Transformation
article

What are the Main Causes of Discontinuous Work?

Danny Murguía, A.K. Pal, Ashan Senel Asmone, Asitha Rathnayake, Campbell Middleton
article en

Abstract

Discontinuous work in construction refers to periods without resource or work continuity, leaving workers without designated locations to perform their tasks.Studies show in many activities idle durations are a significant portion of total work.Caused by poor production system design in projects, discontinuous work is a major cause of low trade productivity.This paper aims to identify factors affecting discontinuous work and quantify their impact.346 datapoints (including 46 superstructure crews across 75 building levels in 10 multistorey buildings in London) were analysed using correlation and regression techniques.Data included crew size, batch size, activity type, work start and end dates.Results showed that reducing the batch size by increasing slab concrete pours per level minimised discontinuities by ensuring more available work locations.Synchronising the production rates of successive crews also reduced discontinuities by limiting idle time for faster crews.Surprisingly, although often considered a cause of discontinuities, out-of-sequence work had no statistically significant relationship with discontinuities.Possibly due to the constraints of superstructure work limiting the out-of-sequence work.Additionally, offsite construction methods exhibited greater variability in discontinuities compared to in-situ methods, likely due to clashes between in-situ activities happening at a different rate of work to offsite activities.

Annual Conference of the International Group for Lean Construction
Openalex Percentile: Top 39%
Digital Economy and Work Transformation
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

What are the Main Causes of Discontinuous Work? — Danny Murguía, A.K. Pal, et al. · Annual Conference of the International Group for Lean Construction (2025) | TGRS Research Map | TGRS