Integrated Forecasting Approach for Takt and Location-Based Scheduling

Takt production is a location-based planning and controlling method that makes schedules more reliable and shortens project durations with no increase in resources by promoting the better use of the workspace. Although several recent publications have discussed takt and how it should be implemented, less attention has been focused on the technical calculations underlying this system, especially during the controlling phase. In contrast, the related location-based management system (LBMS) has well-developed technical calculations for both the planning and controlling phases based on the critical path method (CPM). This paper aims to develop a technical system for takt production by analyzing the conceptual differences between LBMS and takt and then adjusting the LBMS calculations to account for these differences. The proposed new technical system can be used to implement CPM, LBMS, or takt, and it allows planners to decide to use different methods for different parts of projects. The system also accommodates the use of the critical path method, making it compatible with contractual clauses that require CPM.

Authors

Institutions

Publication Details

Journal
Journal of Construction Engineering and Management
Published
2025-09-24
DOI
https://doi.org/10.1061/jcemd4.coeng-16877
Primary Topic
Advanced Manufacturing and Logistics Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Integrated Forecasting Approach for Takt and Location-Based Scheduling

Olli Seppänen
Journal of Construction Engineering and Management
Advanced Manufacturing and Logistics Optimization
article

Integrated Forecasting Approach for Takt and Location-Based Scheduling

Olli Seppänen
article en

Abstract

Takt production is a location-based planning and controlling method that makes schedules more reliable and shortens project durations with no increase in resources by promoting the better use of the workspace. Although several recent publications have discussed takt and how it should be implemented, less attention has been focused on the technical calculations underlying this system, especially during the controlling phase. In contrast, the related location-based management system (LBMS) has well-developed technical calculations for both the planning and controlling phases based on the critical path method (CPM). This paper aims to develop a technical system for takt production by analyzing the conceptual differences between LBMS and takt and then adjusting the LBMS calculations to account for these differences. The proposed new technical system can be used to implement CPM, LBMS, or takt, and it allows planners to decide to use different methods for different parts of projects. The system also accommodates the use of the critical path method, making it compatible with contractual clauses that require CPM.

Journal of Construction Engineering and ManagementVol. 151(12)
Aalto University (FI)
Openalex Percentile: Top 63%
Advanced Manufacturing and Logistics Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.