Acceleration of Modular Oil and Gas Project Duration Using the Time-Cost Trade-Off Method

Floating Production Storage and Offloading (FPSO) is an offshore floating platform designed to process and store oil Floating Production Storage and Offloading (FPSO) is a type of floating offshore platform that functions to process and store oil and gas before being distributed to consumers. A critical component of the FPSO, designed to ensure the product can be safely processed and transported, is the topside module. Currently, the Seawater Filtration Module project is facing delay challenges that impact both project cost and completion time. Using the existing case study, this research applies the Critical Path Method (CPM) to identify the critical path within the overall project schedule, as well as the Program Evaluation and Review Technique (PERT) to manage uncertainties in the completion time of critical activities. To evaluate the acceleration strategy with consideration of additional costs, the Time-Cost Trade-Off (TCTO) method is employed. The research findings indicate that the project experienced a 51-day delay from the original schedule, which targeted completion by January 31, 2024. A total of 11 activities were identified as part of the critical path contributing to the delay. To address this issue, acceleration was carried out by adding labor based on the productivity of each activity. The results show that the addition of 17 workers successfully reduced the duration of critical activities from 721 days to 670 days. Probability analysis indicated a success rate of 82.64% for the acceleration effort. Meanwhile, the cost calculation showed that the acceleration required an additional expense of Rp 30,913,709.

Authors

Institutions

Publication Details

Journal
Journal La Multiapp
Published
2025-09-23
DOI
https://doi.org/10.37899/journallamultiapp.v6i5.2307
Primary Topic
Reservoir Engineering and Simulation Methods
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Acceleration of Modular Oil and Gas Project Duration Using the Time-Cost Trade-Off Method

Silvianita Silvianita, Muhammad Iqbal
Journal La Multiapp
Reservoir Engineering and Simulation Methods
article

Acceleration of Modular Oil and Gas Project Duration Using the Time-Cost Trade-Off Method

Silvianita Silvianita, Muhammad Iqbal
article en

Abstract

Floating Production Storage and Offloading (FPSO) is an offshore floating platform designed to process and store oil Floating Production Storage and Offloading (FPSO) is a type of floating offshore platform that functions to process and store oil and gas before being distributed to consumers. A critical component of the FPSO, designed to ensure the product can be safely processed and transported, is the topside module. Currently, the Seawater Filtration Module project is facing delay challenges that impact both project cost and completion time. Using the existing case study, this research applies the Critical Path Method (CPM) to identify the critical path within the overall project schedule, as well as the Program Evaluation and Review Technique (PERT) to manage uncertainties in the completion time of critical activities. To evaluate the acceleration strategy with consideration of additional costs, the Time-Cost Trade-Off (TCTO) method is employed. The research findings indicate that the project experienced a 51-day delay from the original schedule, which targeted completion by January 31, 2024. A total of 11 activities were identified as part of the critical path contributing to the delay. To address this issue, acceleration was carried out by adding labor based on the productivity of each activity. The results show that the addition of 17 workers successfully reduced the duration of critical activities from 721 days to 670 days. Probability analysis indicated a success rate of 82.64% for the acceleration effort. Meanwhile, the cost calculation showed that the acceleration required an additional expense of Rp 30,913,709.

Journal La MultiappVol. 6(5)
Sepuluh Nopember Institute of Technology (ID)
Openalex Percentile: Top 68%
Reservoir Engineering and Simulation Methods
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.