Analisis Produktivitas Alat Gali Muat dan Alat Angkut pada Kegiatan Pengangkutan Batubara di PT Lematang Coal Lestari (LCL)

The analysis of the productivity of mechanical tools at PT Lematang Coal Lestari (LCL) aims to be an evaluation material for the company for the performance of heavy equipment in the coal transportation process. The results showed an MF value of 0.67 which indicates a work imbalance, where the digging and loading equipment works less than 100% while the transportation equipment works 100%. The productivity of the loading digging equipment reached 310.83 tons/hour with a monthly yield of 139,873.5 tons. Meanwhile, transportation equipment is only 208.40 tons/hour or 93,780 tons/month. The company's production target of 150,000 tons/month has not been achieved because work efficiency is still low, which is 76%. The main obstacles come from the uphill, muddy road conditions and loading patterns that cause waiting times. Efforts to improve the work system are needed to improve work efficiency and achieve production targets.

Authors

Publication Details

Journal
Jurnal Inovasi Global
Published
2025-09-22
DOI
https://doi.org/10.58344/jig.v3i9.418
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analisis Produktivitas Alat Gali Muat dan Alat Angkut pada Kegiatan Pengangkutan Batubara di PT Lematang Coal Lestari (LCL)

Aditya Aditya, Dedi Yansen
Jurnal Inovasi Global
Management and Optimization Techniques
article

Analisis Produktivitas Alat Gali Muat dan Alat Angkut pada Kegiatan Pengangkutan Batubara di PT Lematang Coal Lestari (LCL)

Aditya Aditya, Dedi Yansen
article en

Abstract

The analysis of the productivity of mechanical tools at PT Lematang Coal Lestari (LCL) aims to be an evaluation material for the company for the performance of heavy equipment in the coal transportation process. The results showed an MF value of 0.67 which indicates a work imbalance, where the digging and loading equipment works less than 100% while the transportation equipment works 100%. The productivity of the loading digging equipment reached 310.83 tons/hour with a monthly yield of 139,873.5 tons. Meanwhile, transportation equipment is only 208.40 tons/hour or 93,780 tons/month. The company's production target of 150,000 tons/month has not been achieved because work efficiency is still low, which is 76%. The main obstacles come from the uphill, muddy road conditions and loading patterns that cause waiting times. Efforts to improve the work system are needed to improve work efficiency and achieve production targets.

Jurnal Inovasi GlobalVol. 3(9)
Openalex Percentile: Top 62%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Analisis Produktivitas Alat Gali Muat dan Alat Angkut pada Kegiatan Pengangkutan Batubara di PT Lematang Coal Lestari (LCL) — Aditya Aditya, Dedi Yansen · Jurnal Inovasi Global (2025) | TGRS Research Map | TGRS