Analysis of the Accelerated Implementation of the North Boulevard Paramount Petals Road and Canal Project Using CPM, PERT And Time Cost Trade Off Integration Methods

The North Boulevard Road and Canal Project in the South Petals area is a project that has been under construction since June 2024 and is the main route for the Paramount Petals neighborhood. This project has a work time agreement of 120 normal days. For this reason, it is very important for the project to be completed on time or faster and not experience delays. In this final project, an analysis of project acceleration is carried out using the Critical Path Method scheduling method to determine the activities that are on the critical path and the Program Evaluation and Review Technique to determine the probability that the project can be completed on time. Based on the analysis carried out, it was found that the CPM duration is 120 days with the probability that it can be completed in 120 days is 50.38%. Then the results of the acceleration analysis using the Time Cost Trade Off method show that the optimal project duration is 100 working days with a normal reduction of Rp. 76,604,480.00 in addition to 1 hour of overtime work.

Authors

Publication Details

Journal
Jurnal Teknik dan Science
Published
2025-09-20
DOI
https://doi.org/10.56127/jts.v4i3.2301
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of the Accelerated Implementation of the North Boulevard Paramount Petals Road and Canal Project Using CPM, PERT And Time Cost Trade Off Integration Methods

Ragil Saputra, Ibnu Fadillah
Jurnal Teknik dan Science
BIM and Construction Integration
article

Analysis of the Accelerated Implementation of the North Boulevard Paramount Petals Road and Canal Project Using CPM, PERT And Time Cost Trade Off Integration Methods

Ragil Saputra, Ibnu Fadillah
article en

Abstract

The North Boulevard Road and Canal Project in the South Petals area is a project that has been under construction since June 2024 and is the main route for the Paramount Petals neighborhood. This project has a work time agreement of 120 normal days. For this reason, it is very important for the project to be completed on time or faster and not experience delays. In this final project, an analysis of project acceleration is carried out using the Critical Path Method scheduling method to determine the activities that are on the critical path and the Program Evaluation and Review Technique to determine the probability that the project can be completed on time. Based on the analysis carried out, it was found that the CPM duration is 120 days with the probability that it can be completed in 120 days is 50.38%. Then the results of the acceleration analysis using the Time Cost Trade Off method show that the optimal project duration is 100 working days with a normal reduction of Rp. 76,604,480.00 in addition to 1 hour of overtime work.

Jurnal Teknik dan ScienceVol. 4(3)
Openalex Percentile: Top 72%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.