Analysis Flood Hidrology Kadumalik Dam in Order to Minimize Flood in Rentang Weir

The Rangang Dam faces a significant risk of flooding due to variations in river discharge, especially in the rainy season with high rainfall. As a mitigation effort, the Kadumalik Dam was built as one of the National Strategic Projects located upstream of the Rendang Dam. This study aims to conduct a hydrological analysis to measure the influence of the construction of the Kadumalik Dam on the reduction of flood discharge in the Rendang Dam. The results of the analysis show that the physical characteristics of the watershed (watershed) greatly influence the flood response. Watersheds with longer rivers (L=130 km) produce sloping hydrographs with a peak discharge (Qp) of 37.21 m³/s/mm. In contrast, watersheds with shorter rivers (L=65 km) showed a faster and sharper response with a peak discharge of 57.81 m³/s/mm. Modeling for the Kadumalik watershed itself, which has an area of 435 km² and a river length of 65 km, resulted in a peak unit discharge (Qp) of 12.29 m³/s/mm which was achieved within 4.97 hours. Further discussion revealed a crucial fact, namely that the catchment watershed of the Kadumalik Dam only covers 12.4% of the total watershed upstream of the Rendang Dam. This implies that although the Kadumalik Dam is effective in reducing flooding from its own watershed, its effect on overall flood mitigation in the Rangeng Dam will be partial.

Authors

Publication Details

Journal
Indonesian Journal of Multidisciplinary Science
Published
2025-09-18
DOI
https://doi.org/10.55324/ijoms.v4i12.1192
Primary Topic
Hydraulic flow and structures
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis Flood Hidrology Kadumalik Dam in Order to Minimize Flood in Rentang Weir

Ananda Mila Andita
Indonesian Journal of Multidisciplinary Science
Hydraulic flow and structures
article

Analysis Flood Hidrology Kadumalik Dam in Order to Minimize Flood in Rentang Weir

Ananda Mila Andita
article en

Abstract

The Rangang Dam faces a significant risk of flooding due to variations in river discharge, especially in the rainy season with high rainfall. As a mitigation effort, the Kadumalik Dam was built as one of the National Strategic Projects located upstream of the Rendang Dam. This study aims to conduct a hydrological analysis to measure the influence of the construction of the Kadumalik Dam on the reduction of flood discharge in the Rendang Dam. The results of the analysis show that the physical characteristics of the watershed (watershed) greatly influence the flood response. Watersheds with longer rivers (L=130 km) produce sloping hydrographs with a peak discharge (Qp) of 37.21 m³/s/mm. In contrast, watersheds with shorter rivers (L=65 km) showed a faster and sharper response with a peak discharge of 57.81 m³/s/mm. Modeling for the Kadumalik watershed itself, which has an area of 435 km² and a river length of 65 km, resulted in a peak unit discharge (Qp) of 12.29 m³/s/mm which was achieved within 4.97 hours. Further discussion revealed a crucial fact, namely that the catchment watershed of the Kadumalik Dam only covers 12.4% of the total watershed upstream of the Rendang Dam. This implies that although the Kadumalik Dam is effective in reducing flooding from its own watershed, its effect on overall flood mitigation in the Rangeng Dam will be partial.

Indonesian Journal of Multidisciplinary ScienceVol. 4(12)
Openalex Percentile: Top 73%
Hydraulic flow and structures
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.