Fitness Check for Power Plants in Distribution Grids for Black Start and Regional Islands

ABSTRACT The fast restoration of the grid infrastructure after a grid failure is essential for a reliable energy supply. In this research, grid restoration by ramp‐up of a 400 MW combined cycle power plant, supported by four hydropower generators (100 MW) and three pumps (23 MVA) in a 110‐kV island grid in Upper Austria, is investigated. The objective is to test ramp‐up feasibility and to develop a simulation model which further is verified by the measurement results from the real‐world field tests. Findings include successful ramp‐up with different inertia scenarios, frequency dips up to 1.15 Hz, and challenges by connecting inverter‐based loads. The study underscores the importance of testing restoration strategies to ensure effective island operation during blackouts and to obtain results for simulation model verification. In addition, the influence of the usage of standard parameters on simulation results, thus insufficient knowledge of the controller parameters of the turbine controller, is analysed.

Authors

Institutions

Publication Details

Journal
IET Generation Transmission & Distribution
Published
2025-01-01
DOI
https://doi.org/10.1049/gtd2.70115
Primary Topic
Microgrid Control and Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Fitness Check for Power Plants in Distribution Grids for Black Start and Regional Islands

Darko Brankovic, Andreas Abart, Robert Schuerhuber, Norbert Rechberger
IET Generation Transmission & Distribution
Microgrid Control and Optimization
article

Fitness Check for Power Plants in Distribution Grids for Black Start and Regional Islands

Darko Brankovic, Andreas Abart, Robert Schuerhuber, Norbert Rechberger
article en

Abstract

ABSTRACT The fast restoration of the grid infrastructure after a grid failure is essential for a reliable energy supply. In this research, grid restoration by ramp‐up of a 400 MW combined cycle power plant, supported by four hydropower generators (100 MW) and three pumps (23 MVA) in a 110‐kV island grid in Upper Austria, is investigated. The objective is to test ramp‐up feasibility and to develop a simulation model which further is verified by the measurement results from the real‐world field tests. Findings include successful ramp‐up with different inertia scenarios, frequency dips up to 1.15 Hz, and challenges by connecting inverter‐based loads. The study underscores the importance of testing restoration strategies to ensure effective island operation during blackouts and to obtain results for simulation model verification. In addition, the influence of the usage of standard parameters on simulation results, thus insufficient knowledge of the controller parameters of the turbine controller, is analysed.

IET Generation Transmission & DistributionVol. 19(1)
Graz University of Technology (AT), University of Education Upper Austria (AT), Austrian Energy Agency (AT)
Openalex Percentile: Top 68%
Microgrid Control and Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Fitness Check for Power Plants in Distribution Grids for Black Start and Regional Islands — Darko Brankovic, Andreas Abart, et al. · IET Generation Transmission & Distribution (2025) | TGRS Research Map | TGRS