Project Performance Evaluation Using Critical Path Method and Earned Value Management: A Comparative Analysis of Road Maintenance Projects in the 4th District of Camarines Sur

Road maintenance projects often face delays and budget overruns due to dispersed works, constrained time windows, and resource limitations. This study evaluates the comparative effectiveness of the Critical Path Method (CPM) and Earned Value Management (EVM), including Earned Schedule (ES), in monitoring the performance of road maintenance projects in the 4th District of Camarines Sur, Philippines. A descriptive–comparative design was applied, analyzing five purposively selected projects through documentary analysis, schedule reconstruction, EVM computation, and key informant validation. Findings reveal that CPM obtained a weighted mean rating of 4.3, emphasizing its strength in identifying critical activities and forecasting schedule delays, while EVM registered a mean of 4.4, highlighting its greater utility in cost efficiency and integrated performance analysis. Notably, the integrated CPM–EVM framework achieved the highest rating of 4.8, underscoring its superior usefulness and potential for institutional adoption in infrastructure project monitoring. The study recommends that the Department of Public Works and Highways (DPWH) institutionalize CPM–EVM integration to enhance accountability, early warning systems, and transparency in project delivery.

Authors

Institutions

Publication Details

Journal
Engineering and Technology Journal
Published
2025-09-16
DOI
https://doi.org/10.47191/etj/v10i09.05
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Project Performance Evaluation Using Critical Path Method and Earned Value Management: A Comparative Analysis of Road Maintenance Projects in the 4th District of Camarines Sur

Rocío de la Iglesia, RCE RMP LPT MSCM Engr. Rey . Rimando
Engineering and Technology Journal
Construction Project Management and Performance
article

Project Performance Evaluation Using Critical Path Method and Earned Value Management: A Comparative Analysis of Road Maintenance Projects in the 4th District of Camarines Sur

Rocío de la Iglesia, RCE RMP LPT MSCM Engr. Rey . Rimando
article en

Abstract

Road maintenance projects often face delays and budget overruns due to dispersed works, constrained time windows, and resource limitations. This study evaluates the comparative effectiveness of the Critical Path Method (CPM) and Earned Value Management (EVM), including Earned Schedule (ES), in monitoring the performance of road maintenance projects in the 4th District of Camarines Sur, Philippines. A descriptive–comparative design was applied, analyzing five purposively selected projects through documentary analysis, schedule reconstruction, EVM computation, and key informant validation. Findings reveal that CPM obtained a weighted mean rating of 4.3, emphasizing its strength in identifying critical activities and forecasting schedule delays, while EVM registered a mean of 4.4, highlighting its greater utility in cost efficiency and integrated performance analysis. Notably, the integrated CPM–EVM framework achieved the highest rating of 4.8, underscoring its superior usefulness and potential for institutional adoption in infrastructure project monitoring. The study recommends that the Department of Public Works and Highways (DPWH) institutionalize CPM–EVM integration to enhance accountability, early warning systems, and transparency in project delivery.

Engineering and Technology JournalVol. 10(09)
Partido State University (PH), Central Bicol State University of Agriculture (PH)
Openalex Percentile: Top 71%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Project Performance Evaluation Using Critical Path Method and Earned Value Management: A Comparative Analysis of Road Maintenance Projects in the 4th District of Camarines Sur — Rocío de la Iglesia, RCE RMP LPT MSCM Engr. Rey . Rimando · Engineering and Technology Journal (2025) | TGRS Research Map | TGRS