Deep reinforcement learning-based schedule optimization for parallel precast production

Purpose With the increasing use of precast concrete elements in off-site construction, optimizing precast component production scheduling (PCPS) has become critical for improving construction efficiency. This study aims to develop a deep reinforcement learning (DRL)-based scheduling optimization method for parallel precast production to minimize earliness and tardiness penalties as well as the makespan. Design/methodology/approach A parallel production process model is developed considering resource constraints, including crew quantities and fixed mold plates. A pre-trained DRL model is employed for rescheduling under varying precast orders with different quantities and due dates. The practicality of this approach is validated using real case data from field studies, comparing its performance with traditional dispatching rules (DPs) and the genetic algorithm (GA). Findings The DRL-based method generates production schedules that are viable for practical applications. Compared to traditional DPs and GA, the proposed approach demonstrates superior stability, enhanced rescheduling capability and reduced computational time. Practical implications The proposed DRL-based scheduling method offers a practical and efficient solution for optimizing precast production scheduling. It enhances decision-making in dynamic construction environments by reducing penalties and makespan while improving scheduling adaptability. Originality/value This study expands the limited research on parallel PCPS by introducing a DRL-based approach, which integrates scheduling optimization with dynamic rescheduling adaptability under real-world conditions.

Authors

Institutions

Publication Details

Journal
Engineering Construction & Architectural Management
Published
2025-08-14
DOI
https://doi.org/10.1108/ecam-03-2025-0429
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Deep reinforcement learning-based schedule optimization for parallel precast production

Khoa N. Le, Anthony Butera, Vivian W.Y. Tam, Jun Wang et al.
Engineering Construction & Architectural Management
BIM and Construction Integration
article

Deep reinforcement learning-based schedule optimization for parallel precast production

Khoa N. Le, Anthony Butera, Vivian W.Y. Tam, Jun Wang, Yuan Yao
article en

Abstract

Purpose With the increasing use of precast concrete elements in off-site construction, optimizing precast component production scheduling (PCPS) has become critical for improving construction efficiency. This study aims to develop a deep reinforcement learning (DRL)-based scheduling optimization method for parallel precast production to minimize earliness and tardiness penalties as well as the makespan. Design/methodology/approach A parallel production process model is developed considering resource constraints, including crew quantities and fixed mold plates. A pre-trained DRL model is employed for rescheduling under varying precast orders with different quantities and due dates. The practicality of this approach is validated using real case data from field studies, comparing its performance with traditional dispatching rules (DPs) and the genetic algorithm (GA). Findings The DRL-based method generates production schedules that are viable for practical applications. Compared to traditional DPs and GA, the proposed approach demonstrates superior stability, enhanced rescheduling capability and reduced computational time. Practical implications The proposed DRL-based scheduling method offers a practical and efficient solution for optimizing precast production scheduling. It enhances decision-making in dynamic construction environments by reducing penalties and makespan while improving scheduling adaptability. Originality/value This study expands the limited research on parallel PCPS by introducing a DRL-based approach, which integrates scheduling optimization with dynamic rescheduling adaptability under real-world conditions.

Engineering Construction & Architectural ManagementVol. 32(13)
Western Sydney University (AU)
Openalex Percentile: Top 73%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Deep reinforcement learning-based schedule optimization for parallel precast production — Khoa N. Le, Anthony Butera, et al. · Engineering Construction & Architectural Management (2025) | TGRS Research Map | TGRS