Research on the strength detection methods of railway tunnel linings

Purpose For the commonly used concrete mix for railway tunnel linings, concrete model specimens were made, and springback and core drilling tests were conducted at different ages. The springback strength was measured to the compressive strength of the core sample with a diameter of 100mm and a height-to-diameter ratio of 1:1. By comparing the measured strength values, the relationship between the measured values under different strength measurement methods was analyzed. Design/methodology/approach A comparative test of the core drilling method and the rebound method was conducted on the side walls of tunnel linings in some under-construction railways to study the feasibility of the rebound method in engineering quality supervision and inspection. Findings Tests showed that the rebound strength was positively correlated with the core drill strength. The core drill test strength was significantly higher than the rebound test strength, and the strength still increased after 56 days of age. The rebound method is suitable for the general survey of concrete strength during the construction process and is not suitable for direct supervision and inspection. Originality/value By studying the correlation of test strength of tunnel lining concrete using two methods, the differences in test results of different methods are proposed to provide a reference for the test and evaluation of tunnel lining strength in railway engineering.

Authors

Institutions

Publication Details

Journal
Railway Sciences
Published
2025-09-09
DOI
https://doi.org/10.1108/rs-08-2025-0026
Primary Topic
Civil and Geotechnical Engineering Research
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Research on the strength detection methods of railway tunnel linings

Won Ho Yang
Railway Sciences
Civil and Geotechnical Engineering Research
article

Research on the strength detection methods of railway tunnel linings

Won Ho Yang
article en

Abstract

Purpose For the commonly used concrete mix for railway tunnel linings, concrete model specimens were made, and springback and core drilling tests were conducted at different ages. The springback strength was measured to the compressive strength of the core sample with a diameter of 100mm and a height-to-diameter ratio of 1:1. By comparing the measured strength values, the relationship between the measured values under different strength measurement methods was analyzed. Design/methodology/approach A comparative test of the core drilling method and the rebound method was conducted on the side walls of tunnel linings in some under-construction railways to study the feasibility of the rebound method in engineering quality supervision and inspection. Findings Tests showed that the rebound strength was positively correlated with the core drill strength. The core drill test strength was significantly higher than the rebound test strength, and the strength still increased after 56 days of age. The rebound method is suitable for the general survey of concrete strength during the construction process and is not suitable for direct supervision and inspection. Originality/value By studying the correlation of test strength of tunnel lining concrete using two methods, the differences in test results of different methods are proposed to provide a reference for the test and evaluation of tunnel lining strength in railway engineering.

Railway SciencesVol. 4(5)
China Academy of Railway Sciences (CN)
Openalex Percentile: Top 53%
Civil and Geotechnical Engineering Research
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.