Research on Construction Period Optimization of High-Rise Buildings Based on Integrated Building Platform Applications

This study optimizes high-rise residential construction schedules using Integrated Building Platforms and genetic algorithms. By analyzing process sequences and overlapping relationships, a schedule optimization model is developed to overcome inefficiencies in traditional sequential methods. The model leverages multi-layer collaboration, enabling parallel and interwoven processes while considering overlapping logic and time constraints. Validated with a real case, the model reduced standard-floor construction from 6 to 4 days (33.3% efficiency gain) and cut idle time by 41%. The approach breaks traditional limitations, maximizing platform advantages for improved resource allocation and process management. The research offers a scientific, efficient scheduling solution for high-rise construction, demonstrating significant theoretical and practical value. It presents a novel optimization method for the building industry.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2025-09-15
DOI
https://doi.org/10.3390/buildings15183338
Citations
2
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
4.21
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Research on Construction Period Optimization of High-Rise Buildings Based on Integrated Building Platform Applications

Chenxi Hu, Qingqing Wu, Shuqiang Wang
2 citations
Buildings
Resource-Constrained Project Scheduling
4.21
article

Research on Construction Period Optimization of High-Rise Buildings Based on Integrated Building Platform Applications

Chenxi Hu, Qingqing Wu, Shuqiang Wang
article en
2 citations

Abstract

This study optimizes high-rise residential construction schedules using Integrated Building Platforms and genetic algorithms. By analyzing process sequences and overlapping relationships, a schedule optimization model is developed to overcome inefficiencies in traditional sequential methods. The model leverages multi-layer collaboration, enabling parallel and interwoven processes while considering overlapping logic and time constraints. Validated with a real case, the model reduced standard-floor construction from 6 to 4 days (33.3% efficiency gain) and cut idle time by 41%. The approach breaks traditional limitations, maximizing platform advantages for improved resource allocation and process management. The research offers a scientific, efficient scheduling solution for high-rise construction, demonstrating significant theoretical and practical value. It presents a novel optimization method for the building industry.

BuildingsVol. 15(18)
Hubei University of Technology (CN)
Openalex Percentile: Top 5%
Resource-Constrained Project Scheduling
4.21
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Research on Construction Period Optimization of High-Rise Buildings Based on Integrated Building Platform Applications — Chenxi Hu, Qingqing Wu, et al. · Buildings (2025) | TGRS Research Map | TGRS