Compressing and Decompressing Activities in Multi-Project Scheduling Under Uncertainty and Resource Flexibility

In multi-project environments characterized by resource constraints and high uncertainty, traditional scheduling approaches often fail to respond effectively to dynamic project conditions. Fixed activity durations and rigid resource allocations limit adaptability, leading to inefficiencies and delays. To address this, the paper proposes a novel heuristic-based scheduling method that compresses and decompresses activity durations dynamically within the context of multi-project scheduling under uncertainty and resource flexibility—while preserving resource and precedence feasibility. The technique integrates Critical Path Method (CPM) calculations with heuristic rules to identify candidate activities whose durations can be reduced or extended based on slack availability and resource effort profiles. The objective is to enhance scheduling flexibility, improve resource utilization, and better align project execution with organizational priorities and sustainability goals. Validated through a case study at an automotive company in Portugal, the method demonstrates its practical effectiveness in recalibrating schedules and balancing resource loads. This contribution offers a timely and necessary innovation for companies aiming to enhance responsiveness and competitiveness in increasingly complex project landscapes. It provides an actionable framework for dynamic schedule adjustment in multi-project environments, helping companies to respond more effectively to uncertainty and resource fluctuations. Importantly, the proposed approach also supports sustainability objectives in new product development and supply chain operations. For practitioners, the method offers a responsive and sustainable planning tool that supports real-time adjustments in project portfolios, enhancing resource visibility and execution resilience. For researchers, the study contributes a reproducible, Python-based implementation grounded in Design Science Research (DSR), addressing gaps in stochastic multi-project scheduling and sustainability-aware planning.

Authors

Institutions

Publication Details

Journal
Sustainability
Published
2025-09-09
DOI
https://doi.org/10.3390/su17188108
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Compressing and Decompressing Activities in Multi-Project Scheduling Under Uncertainty and Resource Flexibility

Filipe Alvelos, Marzieh Aghileh, Odete Lopes, Anabela Tereso
1 links
Sustainability
Resource-Constrained Project Scheduling
article

Compressing and Decompressing Activities in Multi-Project Scheduling Under Uncertainty and Resource Flexibility

Filipe Alvelos, Marzieh Aghileh, Odete Lopes, Anabela Tereso
article en

Abstract

In multi-project environments characterized by resource constraints and high uncertainty, traditional scheduling approaches often fail to respond effectively to dynamic project conditions. Fixed activity durations and rigid resource allocations limit adaptability, leading to inefficiencies and delays. To address this, the paper proposes a novel heuristic-based scheduling method that compresses and decompresses activity durations dynamically within the context of multi-project scheduling under uncertainty and resource flexibility—while preserving resource and precedence feasibility. The technique integrates Critical Path Method (CPM) calculations with heuristic rules to identify candidate activities whose durations can be reduced or extended based on slack availability and resource effort profiles. The objective is to enhance scheduling flexibility, improve resource utilization, and better align project execution with organizational priorities and sustainability goals. Validated through a case study at an automotive company in Portugal, the method demonstrates its practical effectiveness in recalibrating schedules and balancing resource loads. This contribution offers a timely and necessary innovation for companies aiming to enhance responsiveness and competitiveness in increasingly complex project landscapes. It provides an actionable framework for dynamic schedule adjustment in multi-project environments, helping companies to respond more effectively to uncertainty and resource fluctuations. Importantly, the proposed approach also supports sustainability objectives in new product development and supply chain operations. For practitioners, the method offers a responsive and sustainable planning tool that supports real-time adjustments in project portfolios, enhancing resource visibility and execution resilience. For researchers, the study contributes a reproducible, Python-based implementation grounded in Design Science Research (DSR), addressing gaps in stochastic multi-project scheduling and sustainability-aware planning.

SustainabilityVol. 17(18)
Polytechnic Institute of Viseu (PT), University of Minho (PT)
Instituto Politécnico de Viseu, Fundação para a Ciência e a Tecnologia
Openalex Percentile: Top 71%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.