Simulation of Mantuil 09 Bridge Construction Scheduling Due to Delays Using Microsoft Project

The construction of the Mantuil 09 Bridge in Banjarmasin is a complex project that requires precise time planning to avoid delays. This study uses Microsoft Project to develop the schedule, identify the critical path, and simulate solutions for delays caused by the late delivery of Grade 345 structural steel materials. The results show that the initial project duration was 215 calendar days with 27 critical activities. After simulating the delay, the project duration increased to 221 days, and the number of critical activities decreased to 21. Solutions such as overtime and changes to working hours successfully returned the project duration to 215 days, in line with the original schedule.

Authors

Institutions

Publication Details

Journal
Jurnal Multidisiplin Madani
Published
2025-08-30
DOI
https://doi.org/10.55927/mudima.v5i8.531
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Simulation of Mantuil 09 Bridge Construction Scheduling Due to Delays Using Microsoft Project

Anisah Fakhriani, Muhammad Humaidi
Jurnal Multidisiplin Madani
BIM and Construction Integration
article

Simulation of Mantuil 09 Bridge Construction Scheduling Due to Delays Using Microsoft Project

Anisah Fakhriani, Muhammad Humaidi
article en

Abstract

The construction of the Mantuil 09 Bridge in Banjarmasin is a complex project that requires precise time planning to avoid delays. This study uses Microsoft Project to develop the schedule, identify the critical path, and simulate solutions for delays caused by the late delivery of Grade 345 structural steel materials. The results show that the initial project duration was 215 calendar days with 27 critical activities. After simulating the delay, the project duration increased to 221 days, and the number of critical activities decreased to 21. Solutions such as overtime and changes to working hours successfully returned the project duration to 215 days, in line with the original schedule.

Jurnal Multidisiplin MadaniVol. 5(8)
Politeknik Negeri Banjarmasin
Openalex Percentile: Top 74%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Simulation of Mantuil 09 Bridge Construction Scheduling Due to Delays Using Microsoft Project — Anisah Fakhriani, Muhammad Humaidi · Jurnal Multidisiplin Madani (2025) | TGRS Research Map | TGRS