EVALUASI PENGENDALIAN WAKTU DAN BIAYA PADA PROYEK KONSTRUKSI MENGGUNAKAN METODE EARNED VALUE ANALYSIS (EVA)

Construction projects often face problems related to the time and cost aspects of their implementation, which lead to irregularities in the form of delays in completion times and cost overruns, this condition indicates the need for the implementation of an effective control system. The Cikupa – Putra Raja road reconstruction project, Pamarican District, Ciamis Regency experienced deviations or delays from the planned schedule in the early stages of its implementation. So this study aims to determine time and cost control using the Earned Value Analysis method to evaluate the performance of project implementation. This study uses a quantitative descriptive method by analyzing secondary data obtained from project documents, including Cost Budget Plan, time schedule, and project weekly reports. The results of the study show that the project was completed according to the schedule and budget plan, namely in 90 days with an actual cost of IDR 2,499,185,000.00. This is indicated by an average positive Schedule Variance value and a Schedule Performance Index value (SPI > 1), this means that the schedule performance is good. From the cost aspect, the average Cost Variance value is positive and the Cost Performance Index value (CPI = 1), indicating that the cost expenditure is in accordance with the budget. Despite delays in the planning schedule in the early stages of its implementation, the project can be controlled without any time and cost. These findings show that the Earned Value Analysis method is effective in controlling and evaluating project performance.

Authors

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-09-09
DOI
https://doi.org/10.25157/jiteks.v2i2.5364
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

EVALUASI PENGENDALIAN WAKTU DAN BIAYA PADA PROYEK KONSTRUKSI MENGGUNAKAN METODE EARNED VALUE ANALYSIS (EVA)

Gini Hartati, Atep Maskur, Rina Nurul Khoerunnisa
Jurnal Ilmiah Teknik Sipil
Occupational Health and Safety Management
article

EVALUASI PENGENDALIAN WAKTU DAN BIAYA PADA PROYEK KONSTRUKSI MENGGUNAKAN METODE EARNED VALUE ANALYSIS (EVA)

Gini Hartati, Atep Maskur, Rina Nurul Khoerunnisa
article en

Abstract

Construction projects often face problems related to the time and cost aspects of their implementation, which lead to irregularities in the form of delays in completion times and cost overruns, this condition indicates the need for the implementation of an effective control system. The Cikupa – Putra Raja road reconstruction project, Pamarican District, Ciamis Regency experienced deviations or delays from the planned schedule in the early stages of its implementation. So this study aims to determine time and cost control using the Earned Value Analysis method to evaluate the performance of project implementation. This study uses a quantitative descriptive method by analyzing secondary data obtained from project documents, including Cost Budget Plan, time schedule, and project weekly reports. The results of the study show that the project was completed according to the schedule and budget plan, namely in 90 days with an actual cost of IDR 2,499,185,000.00. This is indicated by an average positive Schedule Variance value and a Schedule Performance Index value (SPI > 1), this means that the schedule performance is good. From the cost aspect, the average Cost Variance value is positive and the Cost Performance Index value (CPI = 1), indicating that the cost expenditure is in accordance with the budget. Despite delays in the planning schedule in the early stages of its implementation, the project can be controlled without any time and cost. These findings show that the Earned Value Analysis method is effective in controlling and evaluating project performance.

Jurnal Ilmiah Teknik SipilVol. 2(2)
Universitas Galuh (ID)
Openalex Percentile: Top 65%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

EVALUASI PENGENDALIAN WAKTU DAN BIAYA PADA PROYEK KONSTRUKSI MENGGUNAKAN METODE EARNED VALUE ANALYSIS (EVA) — Gini Hartati, Atep Maskur, et al. · Jurnal Ilmiah Teknik Sipil (2025) | TGRS Research Map | TGRS