Research on Integral Splicing Design and Construction Technology for Two Separate Spans of a Prestressed Concrete Continuous Rigid-Frame Bridge

For an existing bridge constructed with separate spans, the ends of adjacent flanges are disconnected. The problem of separated driving may occur at the bridgehead position after traffic conversion. The idea of integral splicing two separate spans of the existing long-span bridge is proposed. Direct crossing of a vehicle between the two separate spans of the existing long-span bridge can be realized. Firstly, the demand for integral splicing of the existing box girder bridge is analyzed using different methods. Then, an integral splicing composite structure (ISC-Structure) is designed and tested, and the corresponding design method is summarized. Finally, the construction technology for the ISC-Structure is optimized based on the actual field conditions. This research shows that the integral splicing demand of the old bridge can be obtained through on-site monitoring at the splicing position. Furthermore, the proposed random traffic flow simulation method can be applied to expand the data volume and verify the validity of the monitoring data. The proposed ISC-Structure meets the transverse splicing requirements of the Xinfengjiang Bridge. It can effectively connect the two separate spans, enabling them to work compositely and improving longitudinal mechanical properties. A layered and segmented construction scheme is proposed, and the relevant construction technology is optimized for the target integral splicing project. The proposed integral splicing design and construction technology can sever as a reference for similar long-span bridge extension projects.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2025-09-05
DOI
https://doi.org/10.3390/buildings15173208
Primary Topic
Structural Engineering and Vibration Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Research on Integral Splicing Design and Construction Technology for Two Separate Spans of a Prestressed Concrete Continuous Rigid-Frame Bridge

Qiao Lu, Jun Song, Chaoyu Zhu, Xuefei Shi et al.
1 links
Buildings
Structural Engineering and Vibration Analysis
article

Research on Integral Splicing Design and Construction Technology for Two Separate Spans of a Prestressed Concrete Continuous Rigid-Frame Bridge

Qiao Lu, Jun Song, Chaoyu Zhu, Xuefei Shi, Yangfan Li, Chenghuan Zhong
article en

Abstract

For an existing bridge constructed with separate spans, the ends of adjacent flanges are disconnected. The problem of separated driving may occur at the bridgehead position after traffic conversion. The idea of integral splicing two separate spans of the existing long-span bridge is proposed. Direct crossing of a vehicle between the two separate spans of the existing long-span bridge can be realized. Firstly, the demand for integral splicing of the existing box girder bridge is analyzed using different methods. Then, an integral splicing composite structure (ISC-Structure) is designed and tested, and the corresponding design method is summarized. Finally, the construction technology for the ISC-Structure is optimized based on the actual field conditions. This research shows that the integral splicing demand of the old bridge can be obtained through on-site monitoring at the splicing position. Furthermore, the proposed random traffic flow simulation method can be applied to expand the data volume and verify the validity of the monitoring data. The proposed ISC-Structure meets the transverse splicing requirements of the Xinfengjiang Bridge. It can effectively connect the two separate spans, enabling them to work compositely and improving longitudinal mechanical properties. A layered and segmented construction scheme is proposed, and the relevant construction technology is optimized for the target integral splicing project. The proposed integral splicing design and construction technology can sever as a reference for similar long-span bridge extension projects.

BuildingsVol. 15(17)
Tongji University (CN)
Openalex Percentile: Top 75%
Structural Engineering and Vibration Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Research on Integral Splicing Design and Construction Technology for Two Separate Spans of a Prestressed Concrete Continuous Rigid-Frame Bridge — Qiao Lu, Jun Song, et al. · Buildings (2025) | TGRS Research Map | TGRS